Central Highlands Development Register

124 downloads 358 Views 917KB Size Report
Oct 6, 2015 - 2016. Emerald Christian. College. Emerald. Renovation of existing Prep ..... mine. Increase life of mine u
• • • • • •











September 2015 Release

DEVELOPMENT BY CATEGORY ($M) Category Not Started

In Progress

$

Retail Construction

$

-

$

-

$

-

$

-

Manufacturing Construction $

-

$

-

$

-

$

-

Residential Construction

$

-

$

$

-

$

Non Residential Construction

$

-

$

$

-

$

Rail

$

-

$

160,000,000

$

-

$

160,000,000

Roads

$

12,875,000

$

8,810,600

$

$

24,385,600

Flood Restoration & Mitigation

$

11,500,000

$

3,900,000

$

-

$

15,400,000

Tourism

$

$

-

$

Mining

$

7,780,000,000

$

Energy

$

948,000,000

$

Water and Sewerage

$

Land

$

CH Subtotal (Projects located outside the CH Region of Significance)

Mining (outside region ie Galilee Basin)

Energy

-

-

$

$

5,130,000

37,950,000 -

35,000,000 -

$

TOTAL

Community Infrastructure

Rail

6,350,000

Completed

$

2,700,000

250,000,000

$

$

4,503,437,750

$

420,250

$

3,500,000

$

$

8,759,145,250

$

4,757,728,350

$

$

4,200,000,000

$

$

14,604,000,000

$

-

$

2,150,000,000

$

2,250,000,000

$

-

$

$

21,054,000,000

$

2,150,000,000

$

Grand Total

$

29,813,145,250

$

6,907,728,350

$

$

17,880,000

37,950,000 -

-

$

8,065,000,000

$

948,000,000

$

4,535,437,750

$

3,920,250

$

13,807,973,600

$

4,200,000,000

-

$

16,754,000,000

-

$

2,250,000,000

$

23,204,000,000

$

37,011,973,600

32,000,000 291,100,000 -

$

Outside CH Subtotal

(partial investment in region )

6,400,000

291,100,000

COMMUNITY INFRASTRUCTURE PROJECT NOT STARTED Toilet Ablution Upgrade

LOCATION Duaringa

Mackenzie Park upgrade to toilet.

Childcare Centre

Emerald

Emerald Airport Runway

Development of new childcare centre.

Emerald

Runway upgrade.

Emerald Christian College

Emerald

Renovation of existing Prep building.

McIndoe Park Master Plan

Emerald

Retirement Village

Emerald

Springsure Showgrounds IN PROGRESS

Springsure

DETAILS

PROPONENT

TIMING

STATUS

$175,000

2015-2016

Deferred until 2015-2016.

$-

2015

$6,000,000

2016-2017

Emerald Christian College

$50,000

2015

Not yet started.

CHRC

$200,000

2014-2015

On hold.

$-

2015

In the planning stages.

$100,000

2014-2015

Deferred until 2015-2016.

CHRC Devcon Property Group CHRC

Upgrades to lighting, car park and fields. Proposal for retirement village in Borilla Street. Approval for 20 units. New clubhouse, preliminary planning.

New Blackwater Aquatic Centre

Blackwater

Concept and development phases for new facility at Hunter Street Sports Complex.

Dingo Town Entrance

Dingo

Erect three (3) Town Entrances with customised artwork.

Emerald Airport Lighting

Emerald

Emerald Airport Carpark

Pitman Properties CHRC

CHRC, BMA

COST (est)

CHRC Approval 25 June 2014. Works to commence in 2016.

Project commenced and detailed design work underway. Construction to commence subject to completion of tender process in 2015 and available funding. Contracts awarded. Completion is estimated to be December 2015.

$14,000,000

2014-2015

CHRC

$100,000

2015

Replace primary cables in conduit for entire airfield lighting second stage.

CHRC

$1,000,000

2014-2015

Project underway and expected completion 2015.

Emerald

Carpark 3 Design and Extend.

CHRC

$1,900,000

2014-2015

Project underway and expected completion October 2015.

Emerald Airport Access Road

Emerald

Airport Access Road intersection with Gregory Highway.

CHRC

$2,000,000

2015-2016

Project commenced and completion expected 2016.

Emerald Saleyards

Emerald

Replacement of Holding Yards. Truck turnaround area - bitumen.

CHRC

$130,000

2015-2016

Project underway and expected completion 2016.

Maranda Heights Park

Emerald

Park infrastructure installation (BBQ and shelter).

CHRC/Portfolio Projects Pty Ltd

$100,000

2015-2016

In Progress.

St Brigid's

Emerald

Further construction of school buildings.

Ram Contractors Qld Pty Ltd

$-

2015

Construction commenced, expected to be completed in 2015.

Emerald Christian College

Emerald

Canteen renovation.

$-

2015

Upgrade completed.

Emerald Christian College

Emerald

Construction of "Little Gems" Kindy and Childcare Centre.

$1,400,000

2015

GP Super Clinic (Central Highlands Health Care)

Emerald

Construct a new GP Super Clinic. Employment: 35 FTE.

$5,000,000

2015

COMPLETED Emerald Christian College Emerald Christian College Fed Govt, CHRC

Sub-total Community Infrastructure Investment:

Construction completed and the two room facility is open for enrolments. Construction completed September 2015. Facility opened to patients 6 October 2015.

$17,880,000

RETAIL CONSTRUCTION PROJECT NOT STARTED Pilot Farm Road development

LOCATION

Emerald

DETAILS

PROPONENT

8000sqm block on Pilot Farm Road, with plans to build a youth centre and haberdashery franchise.

Pitman Properties

COST (est)

TIMING

STATUS

$-

TBA

CHRC - Material Change of Use approval 25/09/2014.

Central Highlands Development Register September 2015

5

RETAIL CONSTRUCTION PROJECT IN PROGRESS

Masters Home Improvement Centre

LOCATION

Emerald

DETAILS

PROPONENT

Construction of home improvement store - offering an array of appliances, lighting dept, mother's room, cafe, garden centre, home Woolworths hardware, kitchens and a trade Limited division - on the corner of Capricorn Hwy and Chalcedony Rd. Sub-total Retail Investment:

COST (est)

TIMING

STATUS

$-

2015

Groundwork has commenced. Further progress on hold.

COST (est)

TIMING

STATUS

$-

TBA

CHRC Approval September 2015.

$-

TBA

Received CHRC development approval 12 August 2015.

TIMING

STATUS

$0

INDUSTRIAL CONSTRUCTION PROJECT NOT STARTED

LOCATION

Lilyvale Solar Farm Project

Tieri

Grain Storage and Rail Transport

Yamala

DETAILS

PROPONENT

FRV, a global solar power company, plans to develop a large FRV scale grid-connected photovoltaic (PV) solar plant. Two-staged subdivision - Stage 1 involves development of grain storage facility and rail siding. 2nd Graincorp stage involves construction of new roads and subdivision of remaining lots. Sub-total Manufacturing Construction Investment:

$0

RESIDENTIAL CONSTRUCTION PROJECT NOT STARTED

LOCATION

DETAILS

PROPONENT

Establishment of 94 houses on blocks from 261sqm to 445sqm with 3 bedroom lowset and twostorey homes. Common area includes pool and bbq. Multiple dwellings development. (13 Dundas Street, Emerald). Landscaping and associated site preparation will need to be conducted.

COST (est)

SCN Pty Ltd

$-

2015

CHRC Approval - 26 February 2014. Amended change approved 9 July 2014. Development yet to commence.

TBA

$-

CHRC Approval

CHRC approval January 2014. 10 x 2 bedroom units.

Citicorp

$-

Subject to demand

Development Approval received. Civil construction to commence in line with future demand.

Development of 10 x 2 bedroom units.

Portfolio Property Investments

$-

2014-2015

CHRC Approval - 11 December 2013.

Tieri

Proposed development of 27 x 4 units.

Mistweft Pty Ltd

$-

Application Approved

Accommodation units (ensuited) Stages 3 and 4 Combined.

O'Brien Street

Capella

Multiple Dwellings, 9 - 11 O'Brien street. 7 x 3 bedroom units.

TBA

$-

Subject to demand

Approved by CHRC January 2014.

City Central Emerald (Loch and Opal Streets)

Emerald

City Central is an estate of 55 allotments. Blocks range from 604 to 1121m2.

Rivergum Homes

$-

2015

Construction is underway.

Emerald

New residential subdivision. 100 lot residential project (1-7acre lots), off Pilot Farm Road.

2013-2015

Under construction. Stage 2A (11 lots) is complete. Stage two to commence in 2015 (subject to demand).

Peak Downs Street

Capella

Dundas Street

Emerald

Highfields Estate (Pilot Farm Road)

Emerald

Proposed development of 1000 lot residential subdivision.

Jade Street (2224) and 26 Amber Street - Unit development

Emerald

Lot 40, North Road Tieri IN PROGRESS

Echidna Valley

TMD Trading Developer: Regional Property Development Corp. Pty Ltd

$-

Central Highlands Development Register September 2015

6

RESIDENTIAL CONSTRUCTION PROJECT IN PROGRESS Highland Park Estate (Codenwarra Road)

LOCATION

Emerald

DETAILS

PROPONENT

15.62ha site, adjoining a major subregional shopping centre. Development includes motel, tavern, 184 allotments, 140 townhouses and a central one-acre park.

Maranda Heights

Emerald

New Residential Estate of Pilot Farm Road.

Mayfair Ridge

Emerald

The estate of over 500 residential allotments for dwellings.

Villas on Rivergum

Emerald

Citimark Properties

COST (est)

TIMING

STATUS

$-

2014-2015

CHRC Approval 14 May 2014. Groundwork commenced. Stages 1, 2 and 7 have sold and settled with construction underway. Stages 3, 4, 5 and 6 have settled with building underway. Stages 11 and 12 (67 lots) available for sale. Stage 1 - 7 and 10 sold. Stage 8 and 11 now selling and construction underway. Stage 9 and 12 not yet released.

Portfolio Projects Pty Ltd

$-

2015

Pratt Property

$-

2014-2015

$37,950,000

2014-2015

Construction underway. Stage 1 sold out. Stage 2 on hold.

COST (est)

TIMING

STATUS

$-

2015

Renegotiating development with CHRC.

$-

2015

CHRC approval.

COST (est)

TIMING

STATUS

$-

TBA

Project development on hold.

End 2015

The first rail works were commissioned in March 2015, export coal railings commenced May 2015. The remaining rail works to match the ramp-up profile will be completed December 2015.

TIMING

STATUS

TBA

Project assessment to continue through the Galilee Basin State Development Area (GBSDA).

GBK 115 unit development on Rivergum Developers/ Drive, Riverview Estate. 5 stage Devcon Building development. Co Sub-total Residential Major Projects Investment:

$37,950,000

WORKFORCE ACCOMMODATION CONSTRUCTION PROJECT NOT STARTED

LOCATION

Duckworth Village, Capricorn Highway

Bluff

Sullivan Street Motel

Emerald

DETAILS

PROPONENT

Accommodation village that will complement existing Bluff Village. Minumbra 504 Units (96 temporary for construction). 102 accommodation units with Devcon restaurant and managers Property Group residence. Sub-total non-residential Major Projects Investment:

$0

RAIL PROJECT NOT STARTED Triumph Creek Loadout Facility

LOCATION

Rolleston

DETAILS

PROPONENT

The rail loadout facility will connect to the Wiggins Island Coal Export Terminal (WICET) using infrastructure already in place.

Bandanna Energy

IN PROGRESS

Wiggins Island Rail Project

Dingo, Bluff, Blackwater

Duplication of 24km track between Dingo-Bluff. Includes 3 new rail bridges beside existing structures. Bauhinia North Upgrade includes Aurizon 2km passing rail loop, 2km rail easement and upgrading 16km access roads. Employment: 180 (con). Sub-total Rail Investment:

$160,000,000

$160,000,000

RAIL (Projects located outside the Central Highlands Region of Significance) PROJECT NOT STARTED

Central Queensland Integrated Rail

LOCATION

Alpha

DETAILS

PROPONENT

Integrated, heavy-haul rail system that will run from the Galilee Basin before linking with existing lines taking coal to the Port of Abbot Point, Hay Point or Dalrymple Bay ports. Employment: 2500 (con); 800 (op).

Aurizon Holdings Limited

COST (est)

$2,000,000,000

Central Highlands Development Register September 2015

7

RAIL (Projects located outside the Central Highlands Region of Significance) PROJECT NOT STARTED

North Galilee Basin Rail Project

LOCATION

Alpha to Abbot Point

DETAILS

PROPONENT

310km standard gauge, multi-user greenfield rail line in CQ, connecting the northern Galilee Basin to the Port of Abbot Point. Employment: 2000 (con); 370 (op).

Adani Mining Pty Ltd

Sub-total Rail Investment outside region:

COST (est)

$2,200,000,000

TIMING

STATUS

TBA

EIS received Commonwealth Minister for Environment's approval on 23 September 2014 subject to conditions.

TIMING

STATUS

$4,200,000,000

Road PROJECT NOT STARTED

LOCATION

DETAILS

PROPONENT

COST (est)

New Street Emerald

Emerald

Flood mitigation works.

CHRC

$1,000,000

2014-2015

Not yet commenced. Council Resolution to proceed on June 24, 2015. Design phase initiated.

Arcadia Valley Road Upgrade

Rolleston

Road Works - Arcadia Valley.

R4R CHRC

$11,800,000

2014-2015

Construction underway. Final 10 km seal expected mid-October, 2015.

Aquarius Street

Tieri

Replace K and C to get water to flow correctly.

CHRC

$75,000

2014-2015

Work commenced April 2015.

Lilyvale Road

Capella

Rehabilitation road.

CHRC

$600,000

2014-2015

Expected completion 2015.

Range123:128 Baranga Road

Central Highlands

Pave and seal.

CHRC

$545,000

2014-2015

In progress.

Comet River Road

Comet

Pave and seal.

CHRC

$774,000

2014-2015

In progress.

Capricorn Highway (Duaringa Emerald)

Duaringa

Relocate hazardous objects close to roads.

DTMR

$318,000

2014-2015

In progress.

Capricorn Highway (Duaringa Emerald)

Duaringa

Rehabilitate and overlay.

DTMR

$2,553,000

2014-2015

In progress.

Capricorn Highway (RockhamptonDuaringa)

Duaringa

Undertake miscellaneous works.

DTMR

$520,000

2014-2015

In progress.

Rehabilitate and overlay.

DTMR

$3,578,000

2014-2015

In progress.

Install/replace signs.

DTMR

$34,000

2014-2015

In progress.

Reseal of road.

CHRC

$255,000

2014-2015

In progress.

Reseal of road.

CHRC

$93,600

2014-2015

In progress.

Reseal of road.

CHRC

$140,000

2014-2015

In progress.

$2,700,000

2014-2015

Completed.

IN PROGRESS

Dawson Highway (Rolleston Springsure) Selma Road Clermont/Rubyval e Road Glendon Road Mt Stuart Road COMPLETED Rifle Range Road

Rubyvale Sapphire Gemfields Tieri Emerald

Rifle Range Road - Riverview to CHRC Pilot Farm Road. Sub-total Roads Investment:

$24,385,600

FLOOD RESTORATION/MITIGATION PROJECT NOT STARTED Emerald Food Mitigation

LOCATION

Emerald

DETAILS

Flood Protection System.

PROPONENT

COST (est)

TIMING

STATUS

CHRC

$11,500,000

2014-2015

Design of levee and early works to be advertised for EOI's in August, 2015.

Central Highlands Development Register September 2015

8

FLOOD RESTORATION/MITIGATION PROJECT IN PROGRESS

LOCATION

DETAILS

PROPONENT

Flood Mitigation Works

Emerald

Other flood mitigation work. CHRC conducted community consultation sessions. An Action Plan involving 3 key strategies developed and are seeking support from other levels of government.

Flood Warning System

Emerald

Install ALERT gauges.

COST (est)

TIMING

STATUS

CHRC

$3,750,000

2013-2015

Commenced GEO technical analysis. Undertaking clearing and thinning of vegetation in Nogoa River.

CHRC

$150,000

2013-2015

Work commenced October 2013 and is continuing.

Sub-total Flood Restoration Investment:

$15,400,000

MINING PROJECT NOT STARTED

LOCATION

DETAILS

PROPONENT

COST (est)

TIMING

STATUS

Stanmore Coal

$869,000,000

2019

Pre FS started Q2 2015.

$-

2025

On hold to align with Curragh Extension project.

Late 2018

Mining leases granted 16/04/2015 for Mackenzie North A (ML70445), D (ML70446), B (ML70448), C (ML70449).

TBA

A mining licence (MDL503) granted for a five year term until October 2019. Drilling campaign finalised.

2017

FS, Final EA issued, objections period closed. Development will be market driven.

Belview Project

Blackwater

New underground project - single longwall. 4Mtpa ROM. Employment: 300 (con); 250 (op).

Curragh (Curragh West)

Blackwater

Open-cut expansion. New capacity Wesfarmers Pty up to 0.3Mt coking. Ltd Employment: 70 (con) e 100 (op).

Jellinbah Mine (Mackenzie North)

Mackenzie Project

Minyango Underground

Washpool Coal Project

Wilpeena

Bluff

Walton

Blackwater

Blackwater

Extension of mining operations at an unchanged production rate. Jellinbah Group Operating in excess of 4.6Mtpa in (Marubeni, line with market demand. Anglo) Employment: 100 (con). New underground project Longwall; Bord and Pillar. The Moreton project has a total JORC compliant Resources resource of 201Mt in inferred resources.

$100,000,000

$860,000,000

Blackwater

New multi-seam underground coal Blackwater Coal project and associated Pty Ltd infrastructure. Capacity total up to (subsidiary of 5Mtpa coking and thermal coal. Caledon Coal Employment: 500 (con); 500 (op Pty Ltd) peak).

Blackwater

New open cut project. Capacity total 3.3Mtpa hard coking coal to be exported through WICET. Approx. 15 year mine life. Employment: 100 (con); 130 (op).

Washpool Coal Pty Ltd (Aquila Resources)

$380,000,000

FYE 2017

The process for gaining the relevant approvals for the mining lease is underway and expected to be concluded in 2016. Construction and production expected 2017.

Blackwater

New project. Open cut and underground. JORC 285Mt total (28.8mt indicated; 257.1mt inferred) PCI, thermal.

Aquila Resources Ltd (100%) (Argos (QLD) Pty Ltd)

$-

TBA

Exploration program underway.

Bluff

New project. MLA lodged 18/2/13. Up to 1.4Mtpa (ROM) PCI. 10-15 year mine life. ML80194. Employment: