Durango Utilities Commission - Meeting Packet - 7/9 ... - City of Durango

1 downloads 183 Views 3MB Size Report
5 days ago - 7. Staff Update. 8. Calendar Review and Agenda Planning. 8.1. a. ... Approval of minutes from May 7, 2018 .
UTILITIES COMMISSION DURANGO PUBLIC LIBRARY, PROGRAM ROOM 3 07/09/2018 4:30 PM AGENDA

1. Call to Order 2. Approval of Minutes 2.1.

a. Approval of minutes from June 4, 2018

3. Announcements 4. Public Participation 5. Old Business/Ongoing Items 5.1.

a. SRWRF (Santa Rita Water Reclamation Facility) design and construction status

5.2.

b. Drought planning/management update

6. New Business 6.1.

2019 Draft Capital Improvement Plan

7. Staff Update 8. Calendar Review and Agenda Planning 8.1.

a. Next scheduled meeting: August 6, 2018

9. Adjournment

1

D$SSURYDORIPLQXWHVIURP-XQH City of Durango Utilities Commission Durango Public Library Program Room 3 Monday, June 4, 2018 4:30-6:00 PM Agenda

I.

Call to order The meeting was called to order at 4:33 p.m. by Chairperson John Ballew. The following Commission members were present: Chairperson John Ballew, Brian Devine, Paul O’Neil, and Council Liaison Dick White. Staff members in attendance included: City Operations Director Levi Lloyd, Utilities Assistant Director Jarrod Biggs, Utilities Project Manager Jennifer Holland, and Customer Service Specialist Marisa Cardin. Commissioner Mike Amato was present for the last thirty minutes of the meeting.

II.

Approval of Minutes a. Approval of minutes from May 7, 2018 Commissioner O’Neil made a motion to approve the minutes from May 7th, 2018 Commission meeting. The motion was seconded by Commissioner Devine. The motion passed.

III.

Announcements Youth Ex-Officio Ian McCourt has graduated. The position has been filled by Owen Eicher for the 2-year term on the Utilities Commission. Chairperson John Ballew requested that the new youth advisor be included on the distribution list.

IV.

Public Participation Public participant Mary Shinn was present. Chairperson John Ballew asked if there was anything the public participant would like to state. No public comment was made during public participation.

V.

Ongoing Business a. SRWRF (Santa Rita Water Reclamation Facility) design and construction status. Assistant Director Biggs provided an update on SRWRF. Water is in the aeration basins and blowers are on as of 4:00 p.m. today. The first two aeration basins are halfway full. Staff will stay until midnight to make sure they are working and filling up, pumping the contents of the current old A-basins into the new ones. Staff continues to water test other two trains and continue work. b. Water meter replacement status.

2

Page 1 of 6

City Operations Director Lloyd provided an update on water meter replacement. The project has been put out to bid. There was a dispute with the original contractor; the City then went on to the second choice. There was an issue with the second choice, so the project is back out to bid. Two vendors are very interested in the project. The City is looking for radios and smart infrastructure. There are 6000 residential accounts; 700 of those accounts that have meters less than 5 years old. c. Performance Dashboard Assistant Director Biggs presented the performance dashboard; the numbers are not finalized. Consumption is average, based on a 5-year average. There was more watering this April than last year due to it being dry. d. Water rate clarifications from last meeting In 2017, the first debt service payments were made on the SRWRF, reflected in the operating ratio. The City issued debt in 2011 to purchase ALP shares and pays debt service annually. The answer to “are we setting rates arbitrarily to prepare for debt service?” is both yes and no – there is no absolute certainty in setting rates and the City included large capital in the budget based on projections of both time and cost – accordingly rates are set to the best of our abilities with the knowledge at hand at that time. We can see our rates and the financials from 2009 to 2014, we were getting by but not ahead. In 2014, City Council made the decision to increase rates which has allowed the City to move from minimal reactionary maintenance toward a proactive maintenance process. Commissioner O’Neil inquired about depreciation. Assistant Director Biggs stated that there are things that continue to work during depreciated lifetime, but we are not getting ahead with the rates being set. City Council has not adopted the rates suggested by the study. Councilor White inquired about what to expect from 2018 financials. Debit service will continue, but what is happening to everything else? Assistant Director Biggs stated that debit service will continue in the operational budget. We are trying to keep things flat, and will see what the new rate study tells us as well. Commissioner O’Neil asked: Are the rates for water going to increase? Where is the water fund going to be when the plant comes in? Will it be the same thing for the sewer? And are we doing this at the right time? The rate increase depended on the plant being further along that it is. Assistant Director Biggs said that he doesn’t presume we will see market rates uptick. Council did not increase rates last year which may decrease the cash available to buy down a loan. On expenditure side, we are trying to keep things even as possible to

3

Page 2 of 6

manage cost. With the sewer plant there are unknowns with how much it will cost to run the plant. i.

City of Durango ALP pumping plant question Assistant Director Biggs stated that there are two pumps in the ALP plant but there is not a pipeline connecting to the terminal reservoir. It’s not that the City doesn’t plan to do it, but with the improvements with Santa Rita pumping plant it reduced the demands and priority to complete the ALP pipe in shorter order. Commissioners inquired about costs. City Operations Director Lloyd noted that the proposed pipeline presents difficulties and expense as its alignment is on a fault line, which will increase the cost of construction. The City is looking for better ways to tie into the raw water line across the river safely and has started preliminary design, however the Ridges Basin Water Treatment Plant is higher priority project and the focus currently to provide redundancy and an opportunity to rehab the current plant. Commissioner Devine inquired about the City’s ability operationally to take water from the Santa Rita plant to Lake Nighthorse. Assistant Director Biggs said that it would require going to water court to change point of diversion, but the City has sufficient water rights and does not need to do that.

ii. Rate Questions Commissioners asked about a credit analysis in relation to the Water Treatment Plant. Staff noted that in a lot of scenarios, the State may force local governments to increase rates. We as a City have done a great job in getting ahead of the game. Durango is not seen as a credit risk. Water and power authority looks at it as “can they make their coverage ratio?”. This is the same thing we are looking at with operating ratio, so no risks are taken with public money. Councilor White asked where we are with the pipe from the dam to the edge of the Bureau of Reclamation property, and how long will it take once we are there to get into deeper planning with WTP? City Operations Director Lloyd responded that the City is waiting on LAPLAWD for their process but we are ready to move forward, looking at an RFP for siting of a plant, the first step, which is scheduled for this year. Once completed, then design and construction to complete in 3-5 years.

4

Page 3 of 6

Commissioner O’Neil asked about the plan regarding plant pressures and how to feed back into the rest of the city. Assistant Director Biggs noted that there are elevation issues. The current plant is at approximately 6980 feet in elevation. The top of lake Nighthorse is approximately 6800 feet. Based on a brief conversation with the City Utilities Engineer, we would require a high capacity transmission line to get it to a higher level. There will be a pumping expense because of the realities of our elevation, which must be a requirement as part of the plan. e. Drought planning update City Operations Director Lloyd stated he will be providing an update to Council at the City Council meeting tonight. The release from Lemon Reservoir is up around 240 CFS. Presently the City gets a full supply of raw water from the Florida. The bypass from Lemon yesterday was at 45 CFS. Once releases from Lemon decrease, then the City will pump from the Animas, and an immediate 10% restriction will go into effect for the four largest users: The Parks and Recreation Department, Durango 9-R Schools, Fort Lewis College, and the Golf Course. Staff will also work with 10 largest commercial users in total. Reducing irrigation water is the most “bang for our buck”. The next step is to use our reservoir management plan and continue to work with large users on a weekly basis. Then we look at reservoir level and we may ask for further reductions. Parks and Recreation has plans to reduce for those reductions, if needed. We are looking at inflows to reservoir, and cascading steps that could get to mandatory restrictions, but working upfront with our largest users, trying to avoid mandatory restrictions. Part of drought plan is looking at long range weather forecast, and the month of July is looking to be a heavier monsoon season. Commissioner O’Neill asked if the reservoir is filled back up. City Operations Director Lloyd reported that the reservoir is at 23 feet. There are still a few issues that are being worked on, but we have asked the state engineer to decide on a resolution because we are in drought conditions and want to fill up. Once we get the ok, we will start to pull out of the Animas to fill to capacity. It will take 2-3 days to fill back up. Commissioner O’Neil asked about the Herald article today about the water dock. Assistant Director Biggs state that the City supplies water to external users from the municipal system. There are over 1200 Water Dock cards today for people to use. The City does not need to continue to add new users at this point. We know how much they use on a given year. If we have a run on our system we cannot manage as well. We want

5

Page 4 of 6

to be neighborly when we can. We will continue to provide water to our current customers, but the new customers we cannot provide for presently. Commissioner Devine asked how external accounts configure into the drought plan. City Operations Director noted that wells are not producing as much, and people are cutting back, using wells for residential use and run to the water dock to feed livestock. The City’s job to provide water to citizens, not livestock. This is a big reason why we are not accepting new users, just for the drought season. Commercial water haulers in the county are current water dock users; they can provide water to users who cannot get water dock cards. Commissioner Devine asked if there is a plan for restrictions on consumption for water dock users as well? City Operations Director Lloyd said that the City would look at working with commercial haulers and doing curtails on that. Assistant Director Biggs noted that the system is not sophisticated enough to differentiate between consumption types. The City does not require registration to use the water dock. Commissioner O’Neil asked if there is a way to start making water dock cards smarter to limit a commercial water dock hauler and start tracking those. Commissioner Devine asked if multiple price tiers like residential users could be used for the water dock. City Operations Director Lloyd said that the system is not sophisticated enough right now to handle those types of items. A proposed CIP project is a new water dock. Assistant Utilities Director Biggs pointed out that out current water dock users pay $0.016/gallon, which is higher than our highest tier or rate ($0.01136/gallon above 18k gallons residential usage in summer). One of the reasons the City is looking at a redesign for the water dock is to do away with the hydrant meter program. We are looking at using two filling stations and we want to be able to have that control if we are in a position critical with supplying residential water. We want a more robust system with complete control to create efficiencies. Chairperson Ballew asked if a Consultant coming for drought plan. Assistant Director Biggs noted that preparation for the drought planning we are doing is taking precedence. VI.

New Business a. Staff and Commissioners discussed dates surrounding the 2019 Capital Budgeting Process.

6

Page 5 of 6

City Operations Director Lloyd stated that staff is in the early stages of looking at CIP and getting proposals to Finance for early review on July 8th. In August, staff will be reviewing CIP Projects. After budget preparation, a draft will be available for review. Councilor White noted it would be handy to have clarity of the CIP projects prior to it going to Council, and being vetted through the Utilities Commission. City Operations Director Lloyd stated a list of CIP projects could be provided at the next meeting. Chairperson Ballew noted to include on the agenda next month: A CIP review for next year. VII.

Staff Update a. Commissioner Devine asked for a staff update on septage haulers. Assistant Director Biggs provided the update. Septage haulers are allowed to dump their septage loads and grease loads at the SRWRF if they have a permit . CDPHE called Jeff Whitman at SRWRF and mentioned that none of our grease haulers have a state license. We discontinued their ability to dump grease until they got a state license. Some haulers will ask “Where should I clean out my truck?” We have directed the haulers to clean their trucks off of the premises. Since then, we have not had any issues that I am aware. Some of this comes down to safety. Septage haulers were crawling into their tanks on our plant site and did not have air monitors to work in that confined space. The City is managing a lot of projects right now. Jennifer Holland, project manager, has been instrumental to help push a lot of the projects forward; many projects are out to bid.

XI.

Calendar Review and Agenda Planning a. Next scheduled meeting: Monday, July 2, 2018 Commissioners decided to move the meeting from July 2nd to July 9th due to the Fourth of July week.

XII.

Adjournment a. Commissioner Devine made a motion to adjourn; Commissioner O’Neil seconded the motion. The meeting was adjourned at 5:47 p.m.

7

Page 6 of 6

2019 Draft Capital Improvement Plan

City of Durango 2018 - June Utilities CIP Progress Report. Water Projects

43

Active Sewer Projects

14

Total

57

Project Status

Count

Project-Funding ID

13

- Project need identified and funding appropriated.

Project Design

26

- Project is in design for engineering, siteplan, or other aspects.

ROW Acquisition / Permitting

1

- Project moving forward to acquire land, right-of-way or permitting necessary to move forward.

RFP Dev. / Contracting

5

- Project having a request for proposal/qualification prepared, contract is out for bid, or contract details are being completed.

Construction

8

- Project construction is underway.

Project Complete

4

- Project is complete.

57

Segments

Project Manager

Status

1033 : Waterline Replacements

Farrell, Patrick

RFP Dev. / Contracting

Project bidding documents completed and turned in to Purchasing, advertising 6/30 & 7/4. Bids due 7/30/18.

$

776,472.00

$

1042 : Water System Telemetry

Ferguson, Dave

Construction

Installed new Cisco switch in T-2 CP. Compressed air, house water pressure, filter Influent turbidity, and plant influent WQ monitoring now in SCADA. Control/Telemetry system design in progress for North & South Santa Rita PRV's

$

220,598.00

$

1043 : Land Acquisition WTP 1044 : WTP Process Revisions

Biggs, Jarrod

Project-Funding ID

Project awaiting RFP for preliminary engineering.

$

94,040.00

$

Ferguson, Dave

Construction

No progress

$

101,130.00

$

1048 : WTP Office Expansion

Ferguson, Dave

Project Design

Plan Review. Eccher working on construction bid set (see also 1064)

$

336,155.00

$

-

1059 : Water Conservation Audits

Ferguson, Dave

Project Design

No progress.

$

103,778.00

$

-

$

1064 : WTP HVAC Insulation Upgrades and New Roof

Ferguson, Dave

Project Design

In progress with Filter Building Office expansion (1048) project. New insulated roof on entire building

$

73,941.00

$

-

$

1066 : ALP Scada Outfall Improvements 1067 : Rogers Reservoir Improvements

Holden, Matt

Project-Funding ID

Project required upon connection to ALP pumping plant.

$

$

-

$

-

$

Ferguson, Dave

Project Design

Design in progress for level monitoring at reservoir outlet structure

$

94,348.00

$

-

$

-

$

94,348.00

Fast, Jason

Project Design

Finishing up the projects electrical design with big picture assistance from FEI, WTP Electrical Upgrades Project engineer.

$

353,719.00

$

1069 : Filter Effluent to Waste System

Ferguson, Dave

Project Design

No progress

$

335,059.00

$

1070 : T1 Flocculator VFD Replacement

Ferguson, Dave

Project Design

Electrical complete. Flocculator basin wall replacement design RFP scheduled for this summer.

$

104,302.00

$

454,797.00

$

24,119.41

$

2,083,884.00

$

4,100.00 65,450.51

1068 : WTP Reclaim/Sludge Management

1071 : WTP Electrical Upgrade 1075 : New 3 MG Tank 1077 : Valve Replacements

1078 : HWy 160 W Water Main Capacity Assurance

1079 : Meter Replacement Program

Ferguson, Dave

Project Design

Holden, Matt

Project Design

Farrell, Patrick

Construction

Holden, Matt

Project Design

Farrell, Patrick

104,650.00

$

Project scoping at Wildcat Tank to install isolation valve enabling future maintenance, and tank control panel with instrumentation for tank level monitoring in SCADA to assure water capacity is provided and monitored as Twin Buttes area grows.

$

49,086.00

$

RFP Dev. / Contracting

Meter Replacement RFP is out for bid, closing on 7/4/2018

$

1,979,287.00

$

Bid planset nearly complete. RFQ for construction out early July. Construction scheduled to begin in September.

$

667,164.00

$

No progress this month

$

116,636.00

$

Tanka Verde Improvement Project awarded to Riley Industrial. Construction August through November, phased for keeping water tank in use through high usage season. PO's issued for City supplied instrumentation and exaust fan.

$

721,010.00

$

$

18,619.00

$

RFP Dev. / Contracting

1084 : WTP Process Piping Rehab

Ferguson, Dave

Project-Funding ID

1088 : Fiber Expansion 29th Street Pipeline 1089 : Terminal Reservoir Dam Repair 1090 : Animas River Repair Work

Filter Building construction completed. Electrical design for Main Distribution Center / generator $ in progress. Project re-scoping proposal from consultant, BHI, is actively under review with consideration of pre-fab vault option by others for potential cost savings. Tank and yard piping plans on hold until $ above re-scoping task completed.

-

YTD Actuals

$

Ferguson, Dave

Ferguson, Dave

2018 FY Budget

To date, 8 valves have been replaced in 2018.

1081 : Florida River Intake @ Rainbow Ranch

1085 : Storage Tank Cleaning Refurbishing

Project Status Notes

RFP Dev. / Contracting

Ferguson, Dave

Construction

Off WTP site work complete. The looping of the fiber from the Miox patch panel to the server(s) to occur during the office expansion construction as the server(s) will be relocated to a new location.

Holden, Matt

Construction

Initial design has been constructed. Additional work may be required to provide proper drainage.

$

243,550.00

$

Army Corp submittal has been put on hold until we address CPW concerns. CPW appears to be declining our request for a design meeting. Strategy for permit approval in progress.

$

91,628.00

Complete with the exception of installing receiver tanks in Chem and Filter Buildings

$

48,274.00

Holden, Matt

Project Design

1091 : Compressed Air System upgrades 1092 : Fencing at WTP 1093 : Site Pipe/Valve Replacement

Ferguson, Dave

Construction

Ferguson, Dave

Project Complete

Ferguson, Dave

Project Design

Funding source of yard piping relocations for 3 MG tank project (in conjunction with 1075)

$

1094 : Upgrade/New Sewer Mains Facility Miox System

Ferguson, Dave

Project Design

In- progress w/3 MG Tank yard piping design (in conjunction with 1075)

$

1096 : Concrete Sidewalks and Aprons

Ferguson, Dave

Project-Funding ID

Concrete placements scheduled for after electrical feeders have been relocated to new Main Electrical Distribution center.

$

0 $

8

-

-

1,457.04 5,636.88

8,822.50

YTD Enc

YTD Available

$

7,994.50

$

768,477.50

$

20,472.99

$

198,667.97

Project Remaining

1%

99%

$

-

$

94,040.00

0%

100%

$

-

$

95,493.12

6%

94%

$

326,327.50

3%

97%

-

$

103,778.00

0%

100%

-

$

73,941.00 0%

100%

8%

92%

2%

98%

$

9,827.50

-

$

15,244.21

$

329,652.29

-

$

25,859.97

$

309,199.03

-

$

$

104,302.00

6,587.50

$

424,090.09

$

45,872.42

$

2,033,911.58

$

10,440.50

$

28,758.99

-

Project Spent

-

$

-

$

49,086.00

0%

100%

5,088.43

$

-

$

1,974,198.57

0%

100%

16,274.81

$

$

644,140.05

3%

97%

$

116,636.00

0%

100%

$

684,198.61

5%

95%

$

18,619.00

0%

100%

$

144,289.18

41%

59%

11,007.58

-

$ $

$

6,749.14 25,803.81

-

82,481.42

$

16,779.40

$

3,880.00

$

2,000.00

$

85,748.00

$

14,120.51

$

-

$

34,153.49

$

-

$

-

$

-

148,565.00

$

-

$

-

$

148,565.00

150,000.00

$

-

$

-

$

150,000.00

56,055.00

$

-

$

-

$

56,055.00

29% #DIV/0!

71% #DIV/0!

0%

100%

0%

100%

Page 1 of 4

Segments 1097 : Pumping Station- PRV's, Pumps, Motors

Project Manager

Status

Project Status Notes

2018 FY Budget

Design is in progress for the North Santa Rita PRV. PO Issued for internal vault retrofit components.

$

212,483.00

Received new spare pump w/mechanical seal.

$

217,821.00

Contract closed. Dewatering permit to be closed too

$

Holden, Matt

Project Design

1100 : Ball Lane Pump Station Upgrades 1101 : River Crossings Replacements Water Mains

Ferguson, Dave

Project-Funding ID

Holden, Matt

Construction

1102 : Tank Chlorine Tablet Feeders

Ferguson, Dave

Project Design

Completed modifications to Grandview Cl Boosting System: Raised Cl tank to supply positive head to chemical feed pump. Remove the draw down tube, strainers, and non-essential fittings to prevent chemical leakage and air infiltration. Appears to have resolved our degassing/air $ lock problem. Modifications to the chemical feed equipment stand are planned to better suit the current configuration.

1104 : Storage Tanks Control Panel Systems

Ferguson, Dave

Project Design

Tanka Verde, Timberline, and Rockridge Tank CP's have been fabricated and received. Tank site design work required for installation at Rockridge & Timberline.

1105 : Drought Plan

$

-

YTD Enc $

YTD Available

9,093.00

$

-

$

858.00

$

-

$

19,489.00

$

-

$

-

$

19,489.00

$

66,325.00

$

-

$

31,240.00

$

35,085.00

No progress - Jarrod Biggs is working on data for the application.

$

50,000.00

47,930.00

$

2,070.00

Project moving forward and funds transferred to 1079 to implement new meter/radio installation.

$

Some funds may be used for Florida Headgate Improvement Project (1081) when contracted.

$

Project Design

1107 : Florida Raw Water Line Replacement

Ferguson, Dave

Project-Funding ID

1109 : CMWTP Site Pipe/Valve Replacement

Ferguson, Dave

Project Design

Funding to support yard piping relocations required for 3 MG Tank project (1075).

1110 : Grandview Pump Station Building Site Improvements

Ferguson, Dave

Project Design

New PO issued to Goff Engineering. Prior plans have been reviewed and redlines provided to Goff.

-

-

$

500,000.00

$

-

$

-

$

500,000.00

0%

100%

$

80,000.00

$

-

$

-

$

80,000.00

0%

100%

$

100,000.00

$

-

$

$

93,360.00

7%

93%

6,640.00

$

$

-

$

1112 : New RBWTP 14.0 MGD WTP 1114 : Ridges Basin WTP Water Main Extension 1115 : CMWTP Coagulant Pumps

No progress. RFP for preliminary engineering needs to be completed.

$

372,773.00

$

440.00

$

Biggs, Jarrod

Project-Funding ID

No progress. RFP for preliminary engineering needs to be completed.

$

920,000.00

$

-

$

Fast, Jason

Project-Funding ID

No Progress

$

75,000.00

$

-

1116 : Land Acquisition

Biggs, Jarrod

Project Complete

Purchase of land at South Durango Tank Completed as joint project with Parks and Recreation

$

27,066.00

$

-

Project Design

Narrow Gauge sewer line replacement - completed in June 2017 with 1/2 mile of 10 inch sewer main replaced from 8th Street south through the train yards to HGWY 160. Next for this CIP is Narrow Gauge heading from 8th north to 12th

$

200,000.00

$

14,437.50

$

10,700.00

Basis of Design report and application to CDPHE under review by staff.

$

1,518,809.00

$

3,626.50

$

8,087.00

Need ROW/easement updates to know if we can proceed with Lower Animas Lift station generator replacement

$

490,632.00

$

Will be completed as part of the SRWRF Construction.

$

8,362.00

No Progress

$

132,985.00

New radio installed for Island Cove lift station monitoring and data collection. Continued improvements in process.

$

279,904.00

$

No Progress

-

2031 : Lift Station Replacement

Biggs, Jarrod

Project Design

2035 : Lift Station Generator Replacements

Farrell, Patrick

ROW Acquisition / Permitting

2041 : SRWWTP Rehab Digester Outer Walls 2043 : Fiber Upgrade and Expansion

Whitman, Jeff

Project Complete

Griffis, Corey

Project-Funding ID

Miera, Clay

Construction

Griffis, Corey

Project-Funding ID

$

200,000.00

$

2047 : Limited Storage Liftstation/Emergency Vaults

Farrell, Patrick

Project Design

Preliminary plan for Lightner Creek LS submitted to CDPHE (see also (2031); Plan for Upper Ramada LS currently in development with Dewberry Engineering.

$

800,000.00

$

2048 : SRWWTP Flood Plain Study

Biggs, Jarrod

Project Design

Survey necessary following completion of the SRWRF

$

50,000.00

Construction of new water main at El Paso was completed 11-10-2017 with the passing of the Bacti tests. Water main brought into service 11-13-2017. Will identify the next replacement for this $ CIP in coming months.

450,000.00

Biggs, Jarrod

Project Complete

2052 : Santa Rita Park Design

Biggs, Jarrod

Project Design

9020 : EIAF 7738 Waste Water Treatment Plant Design

Boysen, Gregg

Project-Funding ID

9025 : State Revolving Loan Fund (SRF - EPA)

Boysen, Gregg

Project-Funding ID

City has provided for demolition of A-Frame at 22nd and Main including sewer line abandonment. The City's contribution from the Utilities Department for purchase of the Old Chamber Bldg. and demo for new site is complete.

$

DHM Design conducting site design for SRWRF with knowledge that SRF funding will only cover replacement of previously existing amenities. Continue to work with P&R staff to identify plan $ aspects for project funding vs. park funding needs. Working with Dewberry to compile admin building design and to complete design of Pressure $ Reduction Vault (North Santa Rita PRV). Project is approximately half way complete. Milestone 1 has been completed with the operation of new aeration basins providing treatment currently. The project continues with sequencing of other $ process buildings.

TOTAL WATER TOTAL SEWER TOTAL UTILITIES DEPARTMENT

$ $ $

9

92% #DIV/0!

$

No progress this month

2051 : Chamber of Commerce Relocation

8% #DIV/0!

$

Project Design

Project Design

96%

-

Project-Funding ID

Farrell, Patrick

4%

378.31

Holden, Matt

2049 : River Crossing Replacements

Project Remaining

$

Biggs, Jarrod

2045 : Sewer Inflow Study

(858.00)

Project Spent

$

-

1111 : College Drive Waterline Upsize

2044 : Collection System Flow Monitoring and Control Syst

201,279.17

16,541.83

RFP Dev. / Contracting

Farrell, Patrick

203,390.00

$

Fast, Jason

2016 : In Situ Sewer Project

$

$

Weiser, Terry

1106 : AMR Upgrades

YTD Actuals

-

171,638.00 48,972,272.00

11,521.50

$

(378.31)

-

$

360,811.50

-

$

920,000.00

$

-

$

$

-

$

96% #DIV/0!

4% #DIV/0!

#DIV/0!

#DIV/0! 3%

97%

75,000.00

0%

100%

27,066.00

0%

100%

$

174,862.50

13%

87%

$

1,507,095.50

1%

99%

-

$

490,632.00

0%

100%

$

-

$

8,362.00

0%

100%

$

-

$

132,985.00

$

-

$

278,304.00

1%

99%

-

$

-

$

200,000.00

0%

100%

-

$

-

$

800,000.00

0%

100%

$

-

$

-

$

50,000.00

0%

100%

$

-

$

-

$

450,000.00

0%

100%

-

$

(12,835.07)

-

$

$

-

$

1,600.00

$

12,835.07

$

$

12,217.94

$

151,509.87

$

7,910.19

$

47,781.50

$

(47,781.50)

$ 31,709,193.88

$

$ $

12,652,586.56

12,167,704.00 $ 260,657.23 $ 300,056.44 $ 53,274,602.00 $ 12,697,303.57 $ 31,927,272.25 $ 65,442,306.00 $ 12,957,960.80 $ 32,227,328.69 $

#DIV/0!

#DIV/0!

95% #DIV/0!

5% #DIV/0!

4,610,491.56

91%

9%

11,606,990.33 8,650,026.18 20,257,016.51

5% 84% 69%

95% 16% 31%

Page 2 of 4

(DRAFT) CAPITAL IMPROVEMENT PLAN SEWER FUND 2019 - 2033 2019 Lift Station Replacement In-Situ Sewer Line Replacement and MH Rehabilitation LiftStation Generators River Crossings Collection System Flow Monitoring and Control System (Flow Meters. I/I) Sewer Inflow Study Limited Storage Liftstation/Emergecny Vaults Fiber upgrade and expansion Santa Rita Utilities Administration Building Vactor Garage Sewer Rate Study Sanitary Sewer Trunkline Maintenence Collections System Assessment SCADA Network Upgrade

Total Capital Needed

Page 1 of 1 Revised 7/3/20183:56 PM

2020

200,000 -

1,250,000 400,000 100,000

2021 400,000 1,250,000 175,000 -

2022 1,250,000 100,000

400,000 50,000

2023 400,000 1,250,000 175,000 400,000 -

2024 1,250,000 -

400,000

2025 400,000 1,250,000

2026 1,250,000

2027 400,000 1,250,000

2028 1,250,000

2029 400,000 1,250,000

400,000

400,000

400,000

400,000

400,000

400,000

2030

2031

2032

2033

1,250,000

200,000

200,000

200,000

1,250,000

200,000

200,000

200,000

50,000

3,750,000 400,000 37,500 400,000 30,000 50,000

4,467,500

2,200,000

2,225,000

1,400,000

2,625,000

10

1,250,000

2,450,000

1,250,000

2,450,000

1,250,000

2,450,000

Page 3 of 4

(DRAFT) CAPITAL IMPROVEMENT PLAN WATER SYSTEMS FUND 2019-2033 Water System Projects Storage Tank Cleaning Refurbishing - 1085 Meter Replacement Program - 1079 CMWTP Site Pipe / Valve Replacement 1093 New RBWTP 14.0 MGD WTP - 1112 Pumping Station- PRV's, pumps, motors - 1097 CMWTP Process Piping Rehab - 1084 Florida Raw Water Line Replacement (engineering) - 1107 CMWTP Fencing - 1092 Valve Replacements - 1077 Water Mains, River Crossings Replacements - 1101 Santa Rita Pump Station Pump Replacement/Rehabilitation - 1082 WTP HVAC Insulation Upgrades and New Roof - 1064 Ridges Basin WTP Water Main Extension - 1065 College Drive Waterline Upsize to 16 inch - 1111 ALP Scada/Outfall Improvements - 1066 CMWTP Fiber Redundancy CMWTP Coagulant Pumps - 1115 Waterline Replacements 1033 Storage Tanks Control Panel Systems - 1104 Water Conservation audits 1059 Terminal Reservoir Expansion - 1108 ALP to Santa Rita River Crossing - 1057 Santa Rita Utilities Administration Building Santa Rita Vactor Gargae CMWTP Paving roads and parking areas - 1096 CMWTP 7 MG Tank Rehab CMWTP Filter Media Replacement CMWTP Replace/upgrade polymer blending chemical feed pump system 1068 - WTP Reclaim/Sludge Management Water Dock Upgrades Water Rate Study Waterline Upsize Distribution System Condition Assessment SCADA Network Upgrade Total Capital Needs

Page 1 of 1 Revised 7/3/20183:59 PM

2019 1,300,000 80,000

100,000

2020

2021 300,000

80,000 13,500,000 100,000 50,000 50,000 100,000

80,000 21,280,000 50,000 450,000 100,000

50,000

50,000

100,000 100,000

100,000

50,000

500,000 100,000 75,000

-

2022

2023 300,000

50,000 300,000 20,000,000 100,000 50,000 100,000 500,000 50,000 80,000

2024

2025 300,000

2026

2027 300,000 200,000

2028 200,000

2029 300000 200,000

2030

2031

2032

2033

200,000

200,000

200,000

200,000

100,000

100,000

100,000

200,000 100,000

100,000

100,000

100000

. 50,000 100,000 500,000

100,000 500,000

100,000 500,000 50,000

50,000 100,000 500,000 50,000

100,000 500,000 50,000

100,000 500,000

500,000

500,000

500,000

500,000

500,000

500,000

500,000

500,000

500,000

1,300,000

1,650,000

1,400,000

1,100,000

950,000

800,000

800,000

800,000

100,000

100,000 50000

600,000

500,000 100,000 75,000

500,000 -

500,000 100,000 75,000

2,300,000 3,750,000 400,000 50,000 300,000

50,000 450,000 60,000 75,000

100,000 350,000 37,500 100,000 30,000 50,000 6,397,500

15,055,000

25,235,000

75,000

22,615,000

1,450,000

11

1,375,000

1,725,000

Page 4 of 4