Ground Beneath Heritage Office Strengthened with Uretek - Mainmark
expanding structural resin, Uretek®. The Mainmark team successfully increased ground capacity to desired compaction levels, delivering the project on time and ...
Ground Beneath Heritage Office Strengthened with Uretek® INDUSTRY
Heritage STRUCTURE
Heritage Office Building PROBLEM
Weak Ground LOCATION
Port Melbourne, VIC, Australia DURATION / YEAR
13 days / May 2016 TECHNOLOGY
Uretek® BUSINESS UNIT
Mainmark Australia
Summary A derelict 1920s art deco office building in the innercity, bayside suburb of Port Melbourne was set to be converted into six apartments. Existing soil beneath the footings of the building was not strong enough to support the additional loads required for the conversion. The ground needed to be consolidated and strengthened, working around difficult soil conditions. Although traditional permeation grouting methods were originally considered, they were found to be unsuitable for the ground conditions. Instead, Mainmark recommended injecting patented expanding structural resin, Uretek®. The Mainmark team successfully increased ground capacity to desired compaction levels, delivering the project on time and on budget.
Objectives Mainmark was required to deliver a solution that would strengthen the ground to support higher loads, work to a tight project schedule and coordinate site access with a range of other trades (including carpenters, demolition teams and screw pile contractors). Site access limitations also had to be accommodated,
with a busy road at the front of the site and building sites on all three boundaries. The working area around the building perimeter to the boundary measured just 1m to 3m.
Solution Mainmark injected approximately 6,000kg of patented expanding structural resin, Uretek®, to a total depth of 2.5m beneath pad footings and strip footings. This was done in a precise and controlled manner, first injecting the resin to one metre and then in 500mm increments thereafter. Once injected, the resin expanded to compact and strengthen the ground. The process was closely monitored to achieve specific, engineered results. A dynamic cone penetration test was completed on each column prior to and after (and in some cases, during) injection, until desired compaction levels were achieved. Results were graphed and presented to the client. As the Uretek® method is clean and involves no water, excavation, cement dust or mess, the project was completed with minimal disruption to schedule and other work groups. The resins used are also non-toxic and environmentally inert.
This 2-storey structure of mostly tilt slab construction had suffered earthquake liquefaction and subsidence. Jet Grouting was used to strengthen the foundation.
along Australia's Main South Railway Line linking capital cities. The bridge piers were deflecting some 300mm on each pass of a train. The footings had cracked ...
Central Railway Station, Sydney, had developed significant voiding in the foundation ground. Void-filling and re-support of the platform was achieved by ...
of non-cohesive soils approximately 7m to 8m below the ground surface within old and abandoned coal workings. Correction was effected by acrylic resin.
wash out, compromising the bridge's foundation. The upper portion of the embankment was unloaded and excavated material was replaced with a pervious ...
Located in Fargo, the most populous city in the USA's state of North Dakota, the Rose. Coulee Bridge is an important thoroughfare for the community. In 2011 ...
Central Railway Station, Sydney, had developed significant voiding in the foundation ground. Void-filling and re-support of the platform was achieved by ...
With a combination of the JOG computer controlled grout and Uretek expanding structural resin injection, the house was back up to level in 18 days. Objectives.
the floors were re-levelled. The work was done so carefully that none of the beautiful stained glass windows was broken or cracked. INDUSTRY. Heritage.
via a fully automated Trimble monitoring system and manual assessment. The high degree of monitoring was a key contributor in achieving such an accurate.
Achrekar didn't mind the ly wheelchairs, compares the ramp while being wheel Master Blaster to Stephen chaired up to the stadium. Hawking while talking of in-.
grout and Uretek expanding structural resin injection, the house was back up to level in 18 days. Objectives. The Earthquake-induced, differential subsidence of ...
MALAY DESAI. Days before his final Test, Tendulkar ensured the entrance to Wankhede ... Sachin Tendulkar's mother Rajni on her wheelchair at the President's ...
Mainmark used its Teretek resin injection solution to provide ground improvement and mitigate liquefaction- induced lateral spreading effects at the property.
A 225mm diameter sewer pipe. The objective of ground strengthening required soil investigations. Five dynamic cone penetrometer tests and one hand auger ...
has found that resin injection is a proven method for increasing soil density, foundation bearing capacity and mitigating liquefaction. Mainmark initiated a series ...
On the notorious âshipwreck coastâ in Southwest. Victoria, Australia, the heritage-listed Warrnambool. Sea Wall, built by hand in 1880 takes the full force of.
Mainmark used a self-levelling cement grout to fill and seal the void in a single day. The placement was continuous, enabling Mainmark to fill the void quickly.