May 10, 2018 - Site Clearance – Demolition. • Site Clearance – Vegetation. • Treatment of Contaminated. Land. En
HS2 meet the contractor day 09:00 - 17:30, Thursday 10 May 2018 The Vox, Birmingham

Construction of the London to Birmingham section of High Speed Two has begun and over the next three years billions of pounds worth of construction works will be tendered to the supply chain. We have appointed three Enabling Works Contractors who are currently looking for suppliers to deliver work in 2018. We have appointed four Main Works Contractors who are currently developing the core railway design and will need to secure their supply chain to start construction in 2019. You will find a list of the key services the Contractors are looking for on Page 2. If your business has any of the capabilities listed, you are invited to register your interest by Friday 30 March to meet these Contractors on a 1-2-1 basis and help deliver Europe’s largest infrastructure programme. Deadline to register interest is Friday 30 March 2018.

Who should register their interest to attend? Micro, small, medium and large companies looking to find out more about the types of work available and how to bid for contracts in the following categories: Drainage • Drainage (pipes in trenches, inspection chambers, ditches, headwalls, etc.) Earthworks • Bulk Earthworks • Ground Anchors • Ground Improvement • Reinforced Earth • Site Clearance – Demolition • Site Clearance – Vegetation • Treatment of Contaminated Land Environmental • Ancient Woodland Relocation • Ecological Mitigation • Ecological Monitoring • Ecological Surveys • River Diversion Specialists • Soft Landscaping / Planting • Tree/ Forestry Surveys • Tree Surgery • Wildlife Habitat Relocation / Creation Fencing • Environmental Barriers • General Fencing • Noise Barriers • Steel Bridge Parapets Materials Supply • • • • • • • • •

 ggregates / Imported Fill A Brickwork / blockwork Bridge Bearings Builders' Merchants Materials Disposal Ducts, Pipes, etc. Formwork Materials Geotextiles Precast Concrete – Cut & Cover Tunnels • Precast Concrete – Drainage • Precast Concrete – Kerbs, Paviors, etc.

• P  recast Concrete – Structures, General • Ready Mixed Concrete • Reinforcing Bars & Mesh • Traffic Management Materials Plant Hire • • • • •

 xcavation Support E Mechanised, Operated, Cranes Mechanised, Operated, Other Mechanised, Small Plant Pumps

Plant Supply • Tunnel Boring Machines (TBM) Preliminaries & Temporary Works • I&M: Network Rail Infrastructure • Noise & Vibration Mitigation • Scaffolding • Site Clearance • Site Compound External Works – external lighting • Site Compound External Works – accessways, hardstandings, fencing, signage, etc. • Site Hoardings • Site Offices • Site Security – CCTV • Site Security – security guards / patrols • Temporary Bridges • Traffic Management Roads & Access • E  arthworks / drainage/ subbase • Kerbing and paviors • Road markings & studs • Signs • Surfacing • Whole scope, discreet offline works packages

Services • N  eedles & Sharps collection / disposal • Pest Control • Rail Logistics • Specialist photography Structures • • • • • • • • • • • • • •

 ored Piling B Bridge Jacking Bridge Launching Cut & Cover Tunnels Demolition Expansion Joints Formwork / Rebar / Concrete Highways incl. Structures Post Tensioning Precast Beams, parapets, abutments Precast Tunnel Segments Sheet Piling Structural Steelwork Waterproofing

Support for Detailed Design • Archaeological  Surveys & Investigations • Drone surveys • Ground Investigation / Site Investigation • Invasive Species Surveys/ Mitigation • Surveys: GPR and Intrusive (Trial Holes) • Topographical Surveys • Traffic Surveys • UXO Surveys Utilities Diversions & Supplies • • • • •

 Electricity Gas TBM Power Supplies Telecomms Water Supply

Register your interest Please follow the link to register your interest between the 12 March and 30 March.

Meetings will be allocated to relevant suppliers on a strictly first come, first served basis.

This is an invitation only event and places will be confirmed week commencing 16 April.

For further information please contact the event team: E: [email protected] T: 0117 906 4520

Main Works Contractors

ALIGN JV

BBV JV

Align is a consortium of three international infrastructure companies; Bouygues Travaux Publics, Sir Robert McAlpine, and VolkerFitzpatrick with combined experience in delivering major projects worldwide. Align has won the HS2- C1 package, consisting of 21.6km of high speed rail; a 3.37kmviaduct; 15.75km twin-tubes tunnel; and several shafts.

Balfour Beatty VINCI is a long-established and successful joint venture in the delivery of critical infrastructure between two global leaders: Balfour Beatty and VINCI Construction.

Please engage with us through demonstrating capabilities for the C1 technical requirements, and an outstanding record in Health & Safety, innovation, diversity, skills, BIM and environmental management and sustainability.

In 2008, Balfour Beatty and VINCI Construction set up a strategic alliance to deliver major infrastructure projects in the UK, including the Channel Tunnel and HS2. Together we have successfully bid and delivered a number of key projects on Crossrail and we were recently awarded a Smart Motorways Programme for Highways England, as well as two major contracts on HS2.

All of our opportunities across C1 are accessible through the CompeteFor portal.

EK JV

SCS JV

The Eiffage Kier joint venture brings together international, market leading technical expertise with an industry leading track record. Our vision is to deliver exceptional services and results that create a safe and sustainable high speed railway and future growth for the UK.

The Skanska, Costain and STRABAG (SCS) joint venture (JV) brings together an industryleading combination of tried, tested and successful partnerships, world-wide high-speed rail experience and extensive international and regional knowledge. The Costain and Skanska JV (CSJV) is currently delivering the Enabling Works contract area South alongside major UK infrastructure projects such as Crossrail. Tunnelling requires tremendous skills and extensive experience from all the partners involved. STRABAG is an experienced contractor, providing technically optimised endto-end tunnelling solutions worldwide.

We harness the best of our suppliers and stakeholders to achieve exceptional results, in a culture where customer excellence, equality, diversity and inclusion flourish. Our collaborative ethos provides a strong platform to deliver innovative, sustainable ‘value for money’ solutions and establish a world-class supply chain.

Enabling Works Contractors

LM JV

FUSION JV

CS JV

LM, a joint venture of Laing O’Rourke and J. Murphy & Sons Limited, has been appointed to deliver HS2 Enabling Works for the northern contract area. The LM team combines worldclass experience in delivering major rail infrastructure projects, with an exceptional track record in engineering innovation, including off-site manufacturing, sustainability, employment, training and skills development.

Fusion connects the expertise, innovation and resources of three world-leading engineering businesses: Morgan Sindall, BAM Nuttall and Ferrovial Agroman (UK). In 2016, Fusion was awarded Area Central of HS2’s enabling works contracts for phase one. Delivering essential preparatory ground works to some 100km of the phase 1 route, before major civil engineering activities begin. Area Central of the phase one route is a vastly rural landscape, and to date Fusion in partnership with its existing supply chain has undertaken a wide range of surveys.

Costain and Skanska have a 30 year history of working together in the UK. In joint venture we successfully deliver many major infrastructure projects, including: the M25 in the 1980s; High Speed 1 in the early 2000s; and London's Crossrail, which will be completed later this year. Our company cultures are aligned and we build sustainable relationships at all levels, with our clients and throughout our supply chain. Our long history of working together means we are trusted to deliver.