Precast Concrete Handling Solutions - Stanton Bonna

the back of a trailer or the requirement for edge protection or fall arrest systems ... Customers are reminded to check prior to delivery they have the ability to ...
425KB Sizes 0 Downloads 64 Views
Updated: Oct 2016

Precast Concrete Handling Solutions Details in this document are ranked in order of recommendation by section colour

Primary Solution

These are recommended options that are safer and more practical as they eliminate the need for personnel to be standing on the back of a trailer or the requirement for edge protection or fall arrest systems

Secondary Solution

Requires staff on trailer

Last Solution

Requires staff on trailer but could become Secondary Solution when used with platforms and edge protection

Advise Against Use

Under no circumstances should this be used

CONTENTS

(Click on the product name to take you to that page)

PRODUCTS

DETAILS

Pipes

Offloading and installation equipment for 300 to 2400 diameter precast concrete pipes

Pipe Lifters

Stanton Bonna range of Pipe Lifters for pipes and fittings

Manholes

Offloading Standard Manhole Rings

4-5

Perfect etc

Offloading Perfect Manhole Rings and Base, Catchpits, Flow Control Units

6-7

Slabs & Fittings

Offloading of Slabs, Gullies, Fittings, Seating Rings

8

Multi Systems

Pallets, Slings, Air Bags

9

PAGE NO

1-2 3

Handling and Off Loading - PIPES

PIPES DN

Pipe Lifter T2-i-A

Pipe Lifter T4-80-A

Stanton Bonna 2-3 Days 500kg Short lengths, some fittings and bends

Stanton Bonna 2-3 Days 650kg Short lengths, some fittings and bends. Can be used with 300's but grater care must be taken

Pipe Lifter T8-90-A

Pipe Lifter T12-100-A

Pipe Lifter AP 1

Pipe Lifter RVD-4-ECO

Lorry Mounted Fork Lift (Moffat)

Stanton Bonna 2-3 Days 1100kg Short lengths, some fittings and bends. Can be used on smaller pipes with some difficulty

MGF, Maybey 2-3 Days 600KG Can also be used for installation

Probst, A PLANT 2-3 Days 914kg Can also be used for installation

Some hauliers 3 days Various Short lengths, some fittings and bends

Pipe Pusher

300 375 450 525 600 675 750 800 900 1050 1200 1400 1500 1600 1800 2000 2200 2400 Supplier Lead Time Self Weight Kg Notes

Primary Solution

Back to Cover Page

Oct 2016

These are recommended options that are safer and more practical as they eliminate the need for personnel to be standing on the back of a trailer or the requirement for edge protection or fall arrest systems Customers are reminded to check prior to delivery they have the ability to safely unload the products.

Stanton Bonna 3-5 days 360kg

Handling and Off Loading - PIPES

PIPES DN

C Beam HLH3A

Platforms

Trailer Edge Protection

Crane offload (Hiab)

Slings

Chains and Lifting Clutches

2-3 days

Stanton Bonna 2-3 days Variable

Stanton Bonna 2-3 days Variable

Supplier Lead Time Self Weight Kg Notes

Secondary Solution Last Solution

Back to Cover Page

Oct 2016

UNDER NO CIRCUMSTANCE SHOULD THEY BE USED

300 375 450 525 600 675 750 800 900 1050 1200 1400 1500 1600 1800 2000 2200 2400

Pipe Hooks

Speedy Hire, Marwood Grantham Fabrications 2-3 days 2-4 weeks 310kg Requires rope guide

Stanton Bonna 2-3 days Limited availability

Limited service. Would be used combined with slings or C beam.

Requires staff on trailer Requires staff on trailer but could become Secondary Solution when used with platforms and edge protection

Unsafe lift & da