Untitled - Environment Clearance

10 downloads 188 Views 29MB Size Report
Indian Remote Sensing satellite IRS LISS III MX digital FCC (False Color. Composite) of current ... based on spectral si
CONTENTS CHAPTER

PARTICULARS

PAGE NO.

PART A

TOR DETAILS

i-xix

1

TOR LETTER ISSUED FROM MoEF

i-v

2

TOR REPLY

vi-xix

PART B

EIA/EMP REPORT

1-199

CHAPTER – I

INTRODUCTION

1-11

CHAPTER – II

PROCESS DESCRIPTION

11-44

CHAPTER – III

DESCRIPTION OF THE ENVIRONMENT

45-106

CHAPTER – IV

ANTICIPATED ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES

CHAPTER – V

107-130

ANALYSIS OF ALTERNATIVES 132 (TECHNOLOGY & SITE)

CHAPTER – VI

ENVIRONMENTAL MONITORING PROGRAMME

133-146

CHAPTER – VII

ADDITIONAL STUDIES

147 -246

CHAPTER – VIII

PROJECT BENEFITS

247-259

CHAPTER – IX

ENVIRONMENTAL COST BENEFIT ANALYSIS

260

CHAPTER – X

ENVIRONMENTAL MANAGEMENT PLAN

261 – 281

CHAPTER – XI

SUMMARY & CONCLUSION

282 – 289

CHAPTER – XII

DISCLOSURE OF CONSULTANTS ENGAGED

290 - 291

a

LIST OF ANNEXURES ANNEXURE NO.

• •

DETAILS

ANNEXURE – 1

DETAILED AAQM TABLES

ANNEXURE – 2 Annexure – 2A Annexure – 2B

WATER ALLOTMENT LETTER FOR PHASE 1 AGREEMENT FOR SUPPLY OF WATER FOR PHASE 2

ANNEXURE – 3

COAL LINKAGE DOCUMENTS

• •

ANNEXURE – 4 Annexure – 4A Annexure – 4B

• •

ANNEXURE – 5 Annexure – 5A Annexure– 5B1, B2, B3

• •

ANNEXURE – 6 Annexure – 6A Annexure – 6B

APPLICATION FOR FOREST LAND SUBMITTED TO FOREST DEPARTMENT APPROVAL LETTER FROM FOREST DEPARTMENT FOR ALLOTMENT OF FOREST LAND ENVIRONMENTAL CLEARANCE LETTER ISSUED FROM MOEF, NEW DELHI FOR PHASE 1 CORRIGENDUMS ISSUED REGARDING EC FOR PHASE-1 RECEIPT OF SUBMISSION OF RECENT COMPLIANCE OF ENVIRONMENTAL CLEARANCE CONDITIONS FOR PHASE 1 RECEIPT OF ESR SUBMISSION

ANNEXURE – 7

CONSENT TO ESTABLISH ISSUED FOR PHASE 1

ANNEXURE – 8

NOC FOR HEIGHT CLEARANCE FOR STACK

ANNEXURE 9

GOVERNMENT LAND PAPERS

ANNEXURE –10

JPL ANNUAL CSR REPORT

ANNEXURE –11

RECEIPT OF SUBMISSION OF JPL ANNUAL CSR REPORT TO COLLECTOR, SEONI

ANNEXURE –12

EXECUTIVE SUMMARY

ANNEXURE – 13

QUESTIONNAIRE

b

List of Abbreviations S. No.

ABBREVIATIONS

EXPANDED FORMS

1.

AAQ

Ambient Air Quality

2.

AAQM

3.

AAS

4.

AERMOD

5.

AHP

Ash Handling Plant

6.

AAS

Atomic Absorption Spectroscopy

7.

BCL

Birla Corporation Limited

8.

BMCR

9.

BOD

Biological Oxygen Demand

10.

BDC

Bag Dust Collector

11.

CEA

Central Electricity Authority

12.

CFBC

Circular Fluidized Bed Combustion

13.

CPP

Captive Power Plant

14.

CPCB

15.

CW SYSTEM

16.

CMB

Central Monitoring Basin

17.

CPCB

Central Pollution Control Board

18.

°C

19.

COC

Cycle Of Concentration

20.

CDM

Clean Development Mechanism

21.

CSR

Corporate Social Responsibilities

22.

CAZRI

23.

CHP

24.

dB

25.

DM Plant

26.

DGMS

Director General of Mines Safety

27.

DMP

Disaster Management Plan

28.

DO

Dissolved Oxygen

29.

EIA

Environmental Impact Assessment

30.

EC

Environmental Clearance

31.

ECC

Emergency Control Center

32.

ESPs

Electrostatic Precipitators

33.

EPS

Electric Power Survey

34.

ETP

Effluent Treatment Plant

35.

ECG

Electrocardiogram

36.

EAC

Expert Appraisal Committee

Ambient Air Quality Monitoring Atomic Absorption Spectroscopy American Meteorological Society/Environmental Protection Agency Regulatory Model

Boiler Max. Continuous Rating

Central Pollution Control Board Cooling Water System

Degree Centigrade

Central Arid Zone Research Institute Coal Handling Plant Decibel Demineralisation Plant

c

37.

EMC

Environmental Monitoring Cell

38.

EMP

Environmental Management Plan

39.

ENE

East of North East

40.

ERDAS

41.

FCC

42.

FE&TI

43.

GHG

Green House Gases

44.

GDP

Gross Domestic Product

45.

GW

Ground Water

46.

GCP

Ground Control Points

47.

GPS

Global Positioning System

48.

GOI

Government of India

49.

GCV

Gross Calorific Value

50.

GC

Gas Chromatography

51.

GWEC

52.

GLC

Ground Level Concentration

53.

HFL

High Flood Level

54.

HVAC

55.

ha

Hectare

56.

Hg

Mercury

57.

HFO

58.

Hz

Hertz

59.

IS

Indian Standards

60.

IMD

61.

KLPD

62.

km

Kilometer

63.

kcal

Kilo Calorie

64.

kWh

Kilo Watt Hour

65.

kg

66.

KL/annum

67.

Ltd

Limited

68.

LU

Land Use

69.

LC

Land Cover

70.

LDO

Light Diesel Oil

71.

LCV

Light Carriage Vehicles

72.

MW

Megawatt

73.

MPPCB

74.

mg

Mille gram

75.

mm

Milli meter

Earth Resources Data Analysis Systems False Color Composite Fire-Explosion and Toxicity Index

Ground water Electrical Conductivity

Heating, Ventilation and Air Conditioning

Heavy Fuel Oil

India Meteorological Department Kilo Liters Per Day

Kilo Gram Kilo Liter Per Annum

Madhya Pradesh Pollution Control Board

d

76.

m³/hr

Cubic meter per hour

77.

MCM

Million Cubic Meter

78.

mS/cm

Milli Siemens per Centimetre

79.

MTPA

Million Tonnes per Annum

80.

MCC

Motor Control Room

81.

NH

National highway

82.

N

83.

NAAQS

North National Ambient Air Quality Standards

84.

Nm3

Newton per metre cube

85.

NW

North West

86.

NRSA

87.

NATMO

88.

NRSC

National Remote Sensing Centre

89.

NCR

North Central Railways

90.

NDIR

Non Depressive Infrared Spectroscopy

91.

O&M

Operation and Maintenance

92.

OSHA

Occupational Safety and Health Administration

93.

OSE

On Site Emergency

94.

PLF

Plant Load Factor

95.

PPE

Personal Protective Equipment

96.

PM10

Particulate Matter less than 10 µg

97.

PM2.5

Particulate Matter less than 2.5 µg

98.

ppm

Parts per million

99.

PAH

Polycyclic Aromatic Hydrocarbons

100.

PPC

Portland Pozzolana Cement

101.

R.S

Railway Station

102.

RF

Reserved Forest

103.

R&R

Rehabilitation and Resettlement

104.

RCC

Reinforced Cement Concrete

105.

SHGs

Self help Groups

106.

SS

Suspended Solids

107.

SW

South -West

108.

ST

Scheduled Tribes

109.

SC

Scheduled Castes

110.

SPM

Suspended Particulate Matter

111.

STP

Sewage Treatment Plant

112.

SOI

Survey of India

113.

SH

State highway

114.

STG

Steam Turbine Generator

National Remote Sensing Agency National Atlas and Thematic Mapping Organization

e

115.

SEIAA

State Environment Impact Assessment Authority

116.

TFT

Thin Film Transistor

117.

ToR

Terms of Reference

118.

TDS

Total Dissolved Solids

119.

UPS

Un-interupted power supply.

120.

UPPCB

Uttar Pradesh Pollution Control Board

121.

USEPA

United States Environmental Protection Agency

122.

UNFCCC

123.

WTP

United Nations Framework Convention for Climate Change Waste Treatment Plant

f

Expansion by addition of 1 x 660 MW Coal based Super Critical TPP (Phase - 2) At Villages Barela and Gorakhpur, Tehsil Ghansore, District Seoni, Madhya Pradesh

ToR Reply of Draft EIA/ EMP Report

ToR Reply Point wise reply of ToR points issued by MoEF, New Delhi vide letter no. J-13012/63/2010 – IA. II (T) dated 8th December, 2010 & addendum in ToR vide letter no. J-13012/63/2010 – IA. II (T) dated 6th September, 2011 for Proposed Expansion by addition of 1 x 660 MW Coal based TPP (Phase - 2) at Villages Barela and Gorakhpur, Tehsil Ghansore, District Seoni, Madhya Pradesh by Jhabua Power Ltd. Ref.: MoEF F. No. J-13012/63/2010 – IA. II (T) dated 8th December, 2010 & addendum in ToR vide letter no. J-13012/63/2010 – IA. II (T) dated 6th September, 2011. With reference to the above subject, we are hereby submitting the reply/clarification of the ToR points issued by MoEF, New Delhi for obtaining Environmental Clearance for Proposed Expansion by addition of 1 x 660 MW Coal based Supercritical TPP (Phase - 2) by Jhabua Power Ltd. The replies are as follows: Point No. 1

Status of compliance to the conditions stipulated in the environmental clearance accorded for Phase-I shall be submitted along with EIA/EMP report.

Reply

Jhabua Power Limited has obtained Environmental clearance for 1 x 600 MW coal based TPP (Phase 1) in villages Barela and Gorakhpur, District Seoni, Madhya Pradesh from Ministry of Environment and Forest, New Delhi in 2010 Vide F.No J 13012/105/2008 - IA.II (T) letter dated 17th February, 2010 and corrigendum. Compliance of the conditions stipulated in EC letter are being submitted to the respective authorities on regular bases. (Copy of the receipt of latest compliance report submitted to the SPCB is enclosed herewith the Final EIA/EMP Report as Annexure - 6.)

Point No. 2

Status of diversion of forests land involved shall be submitted.

Reply

3.88 hectare of forest land has been awarded to Jhabua Power Limited. Requisite document has been annexed as Annexure- 4.

Point No. 3

Vision document specifying prospective long term plan of the site shall be formulated and submitted.

Reply

Vision document will include the following: "To Create Lasting Value" We strive to create lasting value for all our stakeholders through extraordinary efforts. With integrity, imagination and respect for individuals. Lasting to us

M/s. Jhabua Power Ltd.

vi

Expansion by addition of 1 x 660 MW Coal based Super Critical TPP (Phase - 2) At Villages Barela and Gorakhpur, Tehsil Ghansore, District Seoni, Madhya Pradesh

ToR Reply of Draft EIA/ EMP Report

means timeless - value that will endure, regardless of changes in our businesses, people, markets or geographies. By constantly setting and redefining the gold standard in every business we operate in, we will create enduring value for our employees, customers, partners, shareholders and society. For our employees value in the form of professional growth, through an enabling work environment, knowledge sharing, implementation of best practices and growth in their personal life. For our customers - value through quality products and services, understanding of their needs and proactively providing solutions, and contributing to their business growth. For our partners - value through building mutually beneficial long term relationships, knowledge sharing and support, and helping them optimise their business potential. For our shareholders value through a high return on investment, a profitable and sustainable growth platform, and developing the spirit of enterprise. For society -value by focusing on the development needs of the communities we engage with, adopting responsible business practices, and making a sustained effort to preserve the environment. Point No. 4

Executive summary of the project indicating relevant details along with photograph of site shall be provided and issues raised in public hearing along with action plan to address the same shall be provided in tabular form including requisite allocation of funds.

Reply

Executive Summary of the project has been prepared and annexed as Annexure 10. Photographs of the existing site are incorporated in page no 17, section 2.2 of Chapter II of Final EIA/EMP Report. Public hearing for the project has been conducted and actual proceedings along with suggestions/objections by participants, video recording, photographs and attendance sheet has been submitted by MPPCB, Bhopal to MoEF.

Point No. 5

Conformity of the site with the prescribed guidelines in terms of distance of 500 m from HFL of the river, highways, railway line shall be shown on the study area map.

Reply

The project site is about 18 km away from NH-7 in SE direction, approx. 3.0 km from Paryat River in ENE direction and ~1km in NE direction from Binaiki Railway Station. Details of the environmental setting of the area have been incorporated in page 5-6 in Chapter I, item no. 1.3 of Final EIA/EMP report.

M/s. Jhabua Power Ltd.

vii

Expansion by addition of 1 x 660 MW Coal based Super Critical TPP (Phase - 2) At Villages Barela and Gorakhpur, Tehsil Ghansore, District Seoni, Madhya Pradesh

Point No. 6

ToR Reply of Draft EIA/ EMP Report

The project proponent shall provide confirmed GPS readings of plant boundary.

Reply

GPS Readings of the Plant boundary are are under: Latitude:

220 43’ 40”N to 220 44’ 20’’ N

Longitude:

790 54’35” E to 790 55’ 35’’ E

The same has been incorporated in page 5 in Chapter I, item no. 1.3 of Final EIA/EMP Report. Point No. 7

Details of acquisition of tribal land and compliance to tribal rights as per existing Central and State legislations as may be applicable shall be submitted.

Reply

There is no displacement of population in the land for the plant. Land oustees have been suitably compensated. CSR initiatives of JPL have been prioritized on local needs which focus on health and sanitation, education, livelihood and women empowerment.

Point No. 8

No water body/nallah (if any) shall be touched. It shall also be ensured that atleast 100 m distance is kept away from the HFL of the nallah (if any) passing in and around the proposed site.

Reply Point No. 9

There is no nallah passing through the project site. Hydro-geological study of the area shall be conducted from an institute/ organisation of repute to assess impact of on ground and surface water regime. Specific mitigation measures shall be spelt out and action plan for implementation of the same shall be provided.

Reply

Hydro-geological study for the project has been conducted by J.M. Environet Pvt. Ltd. The same is incorporated in page 218-229 of Chapter VII, Item no. 7.5 of Final EIA/EMP report.

Point No. 10

Source sustainability study of water requirement shall be carried out by an institute of repute. The study shall also specify the source of water for meeting the requirement during lean season and proposed plan of action.

Reply

Total water requirement for the proposed expansion project will be 15.33 MCM (23 MCM for Phase 1 & 15.33 MCM for phase 2). The same will be sourced from Bargi Reservoir existing about 10 km away from the project sit in NE direction.

M/s. Jhabua Power Ltd.

viii

Expansion by addition of 1 x 660 MW Coal based Super Critical TPP (Phase - 2) At Villages Barela and Gorakhpur, Tehsil Ghansore, District Seoni, Madhya Pradesh

ToR Reply of Draft EIA/ EMP Report

Permission for 23 MCM/annum has been obtained from Department of Water Resources, MP vide letter no. V.P.C.B./31/Tak/State Govt. – 162/08/86 dated 06.02.09. (Copy enclosed as Annexure 2A). An agreement has been signed between Narmada Valley Development Authority and M/s Jhabua Power Limited on 21’st Feb. 2011 for 16.88 MCM/ annum of water withdrawal from Bargi Reservior (Copy enclosed as Annexure – 2B). Point No. 11

Study on the impact on catchment area of the river due to proposed withdrawal of such huge quantity of water for running the power plant shall be carried out and submitted.

Reply

Hydro-geological study of the area has been carried out and containing all

the

above mentioned details. The same is incorporated in page 218-229 of Chapter VII, Item no. 7.5 of Final EIA/EMP report. Point No. 12

Source of water and its availability. Commitment regarding availability of requisite quantity of water from the competent authority shall be provided along with firm linkage.

Reply

Total water requirement after the proposed expansion project will be 38.33 MCM (23 MCM for Phase 1 & 15.33 MCM for phase 2). The same will be sourced from Bargi Reservoir existing about 10 km away from the project sit in NE direction. Permission for 23 MCM/annum has been obtained from Department of Water Resources, MP vide letter no. V.P.C.B./31/Tak/State Govt. – 162/08/86 dated 06.02.09. (Copy enclosed as Annexure 2A.) An agreement has been signed between Narmada Valley Development Authority and M/s Jhabua Power Limited on 21’st Feb. 2011 for 16.88 MCM/ annum of water withdrawal from Bargi Reservior (Copy enclosed as Annexure – 2B).

Point No. 13

Detailed plan for carrying out rainwater harvesting and proposed utilisation in the plant shall be provided.

Reply

Detailed rainwater harvesting Plan has been prepared for the project. The same is incorporated in page no.229-238 of Chapter VII, Item no. 7.5 of Final EIA/EMP report.

Point No. 14

Feasibility of zero discharge shall be examined and detailed justification shall be submitted if in case the same is not possible. Proposed discharge (if

M/s. Jhabua Power Ltd.

ix

Expansion by addition of 1 x 660 MW Coal based Super Critical TPP (Phase - 2) At Villages Barela and Gorakhpur, Tehsil Ghansore, District Seoni, Madhya Pradesh

ToR Reply of Draft EIA/ EMP Report

any), its quantity, quality and point of discharge, users downstream etc. shall be provided. Reply

Feasibility of Zero effluent discharge has been examined. The Final effluent will have pH in the range of 6.5 to 8.5 and suspended solids below 100 ppm concentration. The details of the same has been incorporated on Item no 10.4.2.2 Pg no. 270 in Chapter X & page no 41-42 of Chapter II ” Process Description” under Item no 2.5 of the Final EIA/ EMP Report.

Point No. 15

Optimization of COC for water conservation. Other water conservation measures proposed in the project should also be given. Quantity of water requirement for the project should be optimized.

Reply

COC for water conservation will be implemented as the liquid effluent from cooling tower blow down will be conserved by maintaining the cycle of concentration at level 5. Details of the same have been given in page 35 of Chapter II, item no. 2.4.3 of Final EIA/EMP Report. Rain water harvesting will be done to conserve the rainwater. Detailed Rain water harvesting Plan has been prepared & the same is incorporated in Chapter VII, item no 7.5, page no. 229-238 of Final EIA/EMP Report.

Point No. 16

Details of water balance taking into account reuse and re-circulation of effluents.

Reply

Detailed water balance diagram is given in page 28 of Chapter II “Process Description”, Item no. 2.3.2 of the Final EIA/EMP Report.

Point No. 17

Detailed plan for conducting monitoring of water quality regularly and mechanism for maintenance of records shall be formulated. Details of methodology and identification of monitoring points (between the plant and drainage in the direction of flow of surface / ground water) shall be submitted. It shall be ensured that parameter to be monitored also include heavy metals in surface and ground water.

Reply

Action Plan for post project monitoring for surface as well as ground water quality has been incorporated in Chapter VI “Environmental Monitoring Programme” of Final EIA/EMP Report.

M/s. Jhabua Power Ltd.

x

Expansion by addition of 1 x 660 MW Coal based Super Critical TPP (Phase - 2) At Villages Barela and Gorakhpur, Tehsil Ghansore, District Seoni, Madhya Pradesh

Point No. 18

ToR Reply of Draft EIA/ EMP Report

Ash pond shall be shifted away as far as possible from any surface water source. The coordinates of the proposed site including location of ash pond shall be submitted along with toposheet.

Reply

Ash pond will be situated within the plant premises. Area earmarked for ash pond (along with geographical coordinates) marked on Topomap has been incorporated in Chapter I, item no. 1.3 Pg No. 5 of Final EIA/EMP Report.

Point No. 19

Action plan for identification of local employable youth for training in skills relevant to the project for eventual employment in the project itself shall be formulated.

Reply

Action plan for identification of employable youth for training has been formulated as per company’s policy. Local people will be preferred on the basis of their qualification and potential. Details of the same are as under: S. No.

Point No. 20

Name of Village

Training Skills

Time Period

1.

Barela

2.

Gorakhpur and Bineki

40 students selected for 2 year ITI of 2 years Electrician and Fitter trade from Government ITI, Ghansore. Students from Gorakhpur, Barela and Bineki 2 years were involved in the batch.

Layout of the plant indicating break-up of plant, green belt, infrastructure, roads etc. shall be provided.

Reply

Layout of the plant indicating break-up of plant area, green belt, infrastructure, roads etc. have been incorporated in Final EIA/EMP report, page 23-25 of Chapter -II “Project Description” under item no. 2.2.2.

Point No. 21

Land requirement for the project shall be optimized. Item wise break up of land requirement and its availability to be furnished. It should also include land to be acquired, if any, for coal transportation system as well as for laying of pipeline including ROW. It may clearly be confirmed that the land including ROW is free of all encumbrances. The issues relating to land acquisition and R&R should be clearly discussed in the EIA report.

Reply

Total land requirement for the proposed Expansion project will be 385.8 acre. The break-up of the landuse for the project is given in the bellow table:

M/s. Jhabua Power Ltd.

xi

Expansion by addition of 1 x 660 MW Coal based Super Critical TPP (Phase - 2) At Villages Barela and Gorakhpur, Tehsil Ghansore, District Seoni, Madhya Pradesh

LAND REQUIREMENT (ACRES)

ToR Reply of Draft EIA/ EMP Report

TYPE OF LAND

PH-I

PH-II

TOTAL LAND REQUIREMENT (ACRES)

PRIVATE (including tribal)

187.04

375.22

562.26

GOVT. FOREST

218.96 NIL

0 9.58

218.96 9.58

TOTAL

406.00

384.80

790.80

STATUS OF LAND ACQUISITION Area in Acres

Phase 1

Phase 2

Total

Scope

Acqd

Bal

Scope

Acqd

Bal

Scope

Acqd

Bal

PrivateLand (including tribal)

187.04

187.04

0

376.21

376.21

0

563.25

563.25

0

Govt Land

218.96

218.96

0

0

0

0

218.96

218.96

0

Forest Land

0

0

0

9.58

9.58

0

9.58

9.58

0

TOTAL

406.00

406.00

0

385.8

385.8

0

791.80

791.80

0

LAND FOR WATER PIPELINE INCLUDING ROW Area in Acres

Required

Acquired

Balance

Forest land

8.75

0

8.75

Government land

1.34

0

1.34

Private land

13.53

0

13.53

Total

23.62

0

23.62

Details have been given in Chapter II, item no. 2.2.2, Pg No. 24-25 of Final EIA/EMP Report.

M/s. Jhabua Power Ltd.

xii

Expansion by addition of 1 x 660 MW Coal based Super Critical TPP (Phase - 2) At Villages Barela and Gorakhpur, Tehsil Ghansore, District Seoni, Madhya Pradesh

Point No. 22

ToR Reply of Draft EIA/ EMP Report

Land use based on satellite imagery or authenticated map indicating drainage, cropping pattern, water bodies (rivers, nallahs, ponds etc.), location of nearest villages, creeks, rivers, reservoirs, national parks, wildlife sanctuaries, tiger reserves, biosphere reserves, heritage sites etc in the study area shall be provided. Location of any National Park, Sanctuary, Elephant/Tiger Reserve (existing as well as proposed), migratory routes, if any, within 10 km of the project site shall be specified and marked on the map duly authenticated by the Chief Wildlife Warden.

Reply

Land use pattern of the study area based on satellite imagery has been incorporated in page no 48-53 of Chapter III, item no.3.3 of Final EIA/EMP Report. No Eco sensitive Zone viz. National Park, Wildlife Sanctuary, Biosphere reserve wildlife corridors falling with the 10 km radius of the project site. Details are given in Chapter I, item no. 1.3 Pg No. 6 of Final EIA/EMP Report.

Point No. 23

Study on land-use pattern in the study area shall be carried out, including identification of common property resources available for conversion into productive land and action plan for abatement and compensation for damage to agricultural land/ common property land (if any) in the nearby villages, due to proposed project shall be prepared.

Reply

Land use pattern of the study area based on satellite imagery has been incorporated in Chapter III, item no.3.3 of Final EIA/EMP Report.

Point No. 24

Detailed socio-economic study shall be carried out for the study area comprising of 10 km from the plant site.

Reply

Socio-economic survey has been conducted through DISHA, NGO. The report contains statistics of households, their livelihood, agriculture pattern, and amenities available in the project area.

Point No. 25

A detailed R&R action plan (as applicable) with time schedule for implementation and also consisting of an in-built monitoring mechanism by an independent third party shall be prepared.

Reply

There is no displacement of population involved in this project. Land oustees will

M/s. Jhabua Power Ltd.

xiii

Expansion by addition of 1 x 660 MW Coal based Super Critical TPP (Phase - 2) At Villages Barela and Gorakhpur, Tehsil Ghansore, District Seoni, Madhya Pradesh

ToR Reply of Draft EIA/ EMP Report

be suitably compensated. JPL has prepared CSR action plan on the bases of local needs, which focus on health, education, livelihood, infrastructure development and environmental conservation. Details of the same are given in Chapter VIII of Final EIA/EMP report. Point No. 26

CSR component shall be prepared based on need based assessment study to be carried out in the study area. Income generating measures which can help in upliftment of poor section of society which is consistent with the traditional skills of the people shall be identified. The programme can include activities such as development of fodder farm, fruit bearing orchards, vocational training etc. In addition, vocational training for individuals shall be imparted so that poor section of society can take up self employment and jobs. Separate budget for community development activities and income generating programmes shall be specified. Financial allocation to be taken up under CSR shall be specified.

Reply

Need assessment and field study conducted through BAIF DEVELOPMENT RESEARCH FOUNDATION, Bhopal for agro. based livelihood development for development of fruit bearing orchard (as per agro climatic conditions of the area) for additional and sustainable livelihood, fodder development, promotion of vermicompost, goat rearing, poultry and other livelihood option among community and work of dairy development through breed improvement in cattle and cattle management aspects. The same has been mentioned in Chapter VIII under Item no 8.1, pg no. 247-249”.

Point No. 27

While formulating CSR schemes it shall be ensured that an in-built monitoring mechanism for the schemes identified is in place and mechanism for conducting annual social audit from the nearest government institute of repute in the region shall be prepared. The project proponent shall also provide plan for the status of implementation of the scheme from time to time.

Reply

Inbuilt mechanism of monitoring is in place and social audit will be done from time to time.

M/s. Jhabua Power Ltd.

xiv

Expansion by addition of 1 x 660 MW Coal based Super Critical TPP (Phase - 2) At Villages Barela and Gorakhpur, Tehsil Ghansore, District Seoni, Madhya Pradesh

Point No. 28

ToR Reply of Draft EIA/ EMP Report

Possibility for adopting nearest three villages shall be explored and details of civic amenities such as roads, drinking water, power etc proposed to be provided at the company’s expenses shall be submitted.

Reply

JPL already has been adopted 3 villages i.e. Barela, Gorakhpur and Binaki. Details of the same have been provided in Chapter VIII of Final EIA/EMP Report.

Point No. 29

Location of intake and outfall points (with coordinates) should be given and the method of disposal of treated waste water from power plant shall be submitted.

Reply

Location of Raw water intake point at boundary (Latitude 22°44'19.41"N and Longitude 79° 55'00"E) has been given in Chapter II, item no. 2.3.2 Pg No. 25-276 of Final EIA/EMP Report. There will be no discharge outside the plant premises, as the treated waste water will be recycled within the plant premises. Details of the waste water management have been provided in Chapter II, item no. 2.5 Pg 41-42 of Final EIA/EMP Report.

Point No. 30

Topography of the area should be given clearly indicating whether the site requires any filling. If so, details of filling, quantity of fill material required, its source, transportation etc. should be given.

Reply

The Project site is having almost a flat terrain, hence does not require any filling.

Point No. 31

One complete season AAQ data (except monsoon) shall be given along with the dates of monitoring. The parameters to be covered shall include SPM, RSPM (PM10, PM2.5), SO2, NOx, Hg and Ozone (ground level). The location of the monitoring stations should be so decided so as to take into consideration the pre-dominant downwind direction, population zone and sensitive receptors including reserved forests. There should be at least one monitoring station each in the upwind and in the pre dominant downwind direction at a location where maximum ground level concentration is likely to occur.

Reply

Ambient air monitoring was carried out at 10 locations for Winter Season (20th October 2010 to 19th January, 2011) within the study area of 10 km to assess the ambient air quality. The dominant wind direction observed during the study period was from NE and therefore one location was selected in downwind direction (SW) for Ambient Air

M/s. Jhabua Power Ltd.

xv

Expansion by addition of 1 x 660 MW Coal based Super Critical TPP (Phase - 2) At Villages Barela and Gorakhpur, Tehsil Ghansore, District Seoni, Madhya Pradesh

ToR Reply of Draft EIA/ EMP Report

Quality Monitoring i.e. Near Railway Line (1.0 km) & upwind direction (NE) i.e. Gorakhpur (0.75 km). Details of the same have been given in chapter 3, item no 3.7 Pg No.71-78 of Final EIA/EMP Report. Point No. 32

Cumulative impact assessment on ambient air quality due to proposed plant and others (including existing as well as other proposed source of emission) shall be carried out and result submitted in the EIA Report. Mitigative measures as necessary shall be clearly spelt out.

Reply

Ambient air quality modelling including cumulative impact assessment on ambient air quality has been conducted for the expansion Coal Based Thermal Power Plant. Details of the same have been incorporated in Chapter IV, item no. 4.4.1 Pg No. 112-117 of Final EIA/EMP Report.

Point No. 33

Impact of the project on the AAQ of the area. Details of the model used and the input data used for modelling should also be provided. The air quality contours may be plotted on a location map showing the location of project site, habitation nearby, sensitive receptors, if any. The wind roses should also be shown on this map.

Reply

Ambient air quality modelling has been conducted for the above said project. Details of the same have been incorporated in Chapter IV, item no. 4.4.2 Pg No. 113-117 of Final EIA/EMP Report. Wind rose has been shown in Chapter III, item no. 3.6.4, page 70.

Point No. 34

Fuel analysis shall be provided. Details of auxillary fuel, if any including its quantity, quality, storage etc should also be given.

Reply

The details of the fuel analysis are given in Chapter II “Process Description”, Item no. 2.3.3.1 Pg No. 29-30 of the Final EIA/EMP report.

Point No. 35

Quantity of fuel required, its source and transportation route and mode and a confirmed fuel linkage documents shall be provided.

Reply

Details of the fuel type, quantity, source, and mode of transportation is given in the table below: S. No. Type of Fuel

Quantity

Source

Transportation

1.

Coal

3.62 MTPA

SECL/ MCL MINES

RAIL

2.

Fuel Oil

2.00ML/KWH

NEARBY MARKET

TANKER

M/s. Jhabua Power Ltd.

xvi

Expansion by addition of 1 x 660 MW Coal based Super Critical TPP (Phase - 2) At Villages Barela and Gorakhpur, Tehsil Ghansore, District Seoni, Madhya Pradesh

ToR Reply of Draft EIA/ EMP Report

Coal Linkage documents are enclosed herewith the Final EIA/EMP Report as Annexure 3. Point No. 36

Details regarding infrastructure facilities such as sanitation, fuel, restroom, medical facilities, safety during construction phase etc. to be provided to the labour force during construction as well as to the casual workers including truck drivers during operation phase.

Reply

JPL provide all basic Infrastructure facilities to the construction labourers. Temporary housing facilities will be provided to the construction workers at planned labour colonies located preferably nearer to project site. Sufficient and appropriate sanitary facilities will be provided in order to maintain hygienic conditions in the camps of construction labours. These facilities will be suitably designed and well maintained so as to minimize adverse impacts on nearby area.

Point No. 37

EMP to mitigate the adverse impacts due to the project along with item wise cost of its implementation.

Reply

Environmental Management Plan for the project has been given in Chapter VIII of Final EIA/EMP Report. About Rs. 327.07 Crores (181.5 crores for phase-1 and 193.0 crores for phase-2) have been earmarked as capital cost for EMP measures. Details have been given in Chapter VI, item no. 6.5 pg no 146 of Final EIA/EMP Report.

Point No. 38

A Disaster Management Plan along with risk assessment study including fire and explosion issues due to storage and use of fuel should be carried out. It should take into account the maximum inventory of storage at site at any point in time. The risk contours should be plotted on the plant layout map clearly showing which of the proposed activities would be affected in case of an accident taking place. Based on the same, proposed safeguard measures should be provided. Measures to guard against fire hazards should also be provided.

Reply

Disaster Management Plan along with risk assessment study including fire and explosion issues due to storage and use of fuel has been prepared & incorporated in Chapter VII “Additional Studies” item no 6.3 pg no 147-148 of the Final EIA/EMP report.

M/s. Jhabua Power Ltd.

xvii

Expansion by addition of 1 x 660 MW Coal based Super Critical TPP (Phase - 2) At Villages Barela and Gorakhpur, Tehsil Ghansore, District Seoni, Madhya Pradesh

Point No. 39

ToR Reply of Draft EIA/ EMP Report

Detailed plan for raising Green belt of 100 m width and consisting of at least 3 tiers around plant boundary with tree density not less than 2500 trees per ha and survival rate at least 75% shall be submitted.

Reply

Out of the total plant area i.e. 791.80 acres (Phase 1: 406.0 acres & Phase 2: 385.8 acres), about 261 acres (134 acres for Phase 1 & 127 acres for Phase 2) of area will be covered under Green Belt /Plantation. Details of the same have been incorporated in Chapter- X “Environmental Management Plan”, item no. 10.4.5 pg no. 275-277 of Final EIA/EMP Report.

Point No. 40

Details of litigation pending or otherwise with respect to project in any courts, tribunal etc. shall be provided.

Reply

There is no litigation pending against the project. Additional Information required: 1.

Is the Project intended to have CDM-intent?

Reply Yes, project is intended to have CDM-intent. A)

Has the PIN submitted to the NCA in the MoEF?

Reply No PIN has been submitted. B)

If not then by when is that expected?

Reply PIN is expected to be submitted within six months from the start of main plant package. Ref.: MoEF F. No. J-13012/63/2010 – IA. II (T) dated 6th September, 2011 Point No. 41

Harnessing solar power within the premises of the plant particularly at available roof tops and other available areas shall be formulated and schedule for implementation shall be submitted along with EIA report.

Reply

JPL proposes to harness solar energy based on photovoltaic technology. Roof top mounted solar PV panels are proposed to be used to power the lighting systems in various buildings/areas in the power plant. The detail of the same has been incorporated under item 7.6 of Chapter 7 of the Final EIA/ EMP Report on page numbers 238.

M/s. Jhabua Power Ltd.

xviii

Expansion by addition of 1 x 660 MW Coal based Super Critical TPP (Phase - 2) At Villages Barela and Gorakhpur, Tehsil Ghansore, District Seoni, Madhya Pradesh

Point No. 42

ToR Reply of Draft EIA/ EMP Report

If the area has tribal population it shall be ensured that the rights of tribals are well protected. The project proponent shall accordingly identify tribal issues under various provisions of the law of the land and provide details.

Reply

Proper care for the rights of tribals will be taken. Tribal issues, if any, shall be addressed and details submitted accordingly.

M/s. Jhabua Power Ltd.

xix

Expansion by addition of 1 x 660 MW Coal Based Super Critical TPP (Phase - 2) At Villages Barela and Gorakhpur, Tehsil Ghansore, District Seoni, Madhya Pradesh Final EIA/EMP Report

CHAPTER–I INTRODUCTION 1.1

PURPOSE OF THE REPORT

Economic, social and environmental change is inherent to development. Whilst development aims to bring about positive change, it can also lead to conflicts. In the past, the promotion of economic growth as the motor for increased well-being was the main development thrust with little sensitivity to adverse social or environmental impacts. The need to avoid adverse impacts and to ensure long term benefits led to the concept of sustainability. Sustainability has been accepted as an essential parameter to assess the development, if the aim of increased well-being and greater equity in fulfilling basic needs is to be met for the present and future generation. Industrialization is one of the components of today’s world development, and sustainability need to be maintained along with. Consequently, there is a need to harmonize developmental activities with the environmental concerns. Environmental Impact Assessment (EIA) is one of the tools available with the planners to achieve the above mentioned goals. An Environmental Impact Assessment (EIA) may be defined as: ”A formal process to predict the environmental consequences of human development activities and to plan appropriate measures to eliminate or reduce adverse effects and to augment positive effects”. EIA is an assessment of the possible impact—positive or negative—that a proposed project may have on the environment, together consisting of the natural, social and economic aspects. The purpose of the assessment is to ensure that decision makers consider the ensuing environmental impacts when deciding whether to proceed with a project. EIA, thus, has three main functions: 

To predict problems,



To find ways to avoid them, and



To enhance positive effects.

M/s. Jhabua Power Ltd.

1

J.M.Environet Pvt. Ltd.

Expansion by addition of 1 x 660 MW Coal Based Super Critical TPP (Phase - 2) At Villages Barela and Gorakhpur, Tehsil Ghansore, District Seoni, Madhya Pradesh Final EIA/EMP Report

To keep the environment congenial for better standard of living, the provisions have been made in the constitution of India and many Enactments have taken place, so that, industrialization may not have adverse impact on the environment. There are many Acts / Rules / Notifications issued by MoEF in this regard, few of them are mentioned below: 

Environment (Protection) Act, 1986;



Environment (Protection) Rules, 1986;



Water (Prevention & Control of Pollution) Act, 1974;



Air (Prevention & Control of Pollution) Act, 1981;



Environmental Impact Assessment (EIA) Notification, dated 14th September 2006.

As per the EIA Notification dated 14th September 2006, it is mandatory to have the Environmental Clearance for any new industry or the expansion of the industry from Ministry of Environment & Forests, Government of India, and New Delhi. The process involves an analysis of the likely impacts on the environment, recording those effects and proposed appropriate control measures and management to ensure a secure, hale and healthy environment in a report (Draft EIA/EMP Report), undertaking a public consultation exercise on the report, taking into account the comments and the report (Final EIA/EMP Report) when making the final decision and informing the public about that decision afterwards. The sole purpose of the EIA/EMP report is to provide a coherent statement of the potential impacts of a proposal and the measures that can be taken to reduce and remedy them. It contains essential information for: 

the proponent to implement the proposal in an environmentally and socially responsible way;



the responsible authority to make an informed decision on the proposal, including the terms and conditions; and



the stakeholders to understand the proposal and its likely impacts on people and the environment.

M/s. Jhabua Power Ltd.

2

J.M.Environet Pvt. Ltd.

Expansion by addition of 1 x 660 MW Coal Based Super Critical TPP (Phase - 2) At Villages Barela and Gorakhpur, Tehsil Ghansore, District Seoni, Madhya Pradesh Final EIA/EMP Report

1.2

IDENTIFICATION OF THE PROJECT AND PROJECT PROPONENT

1.2.1

ABOUT THE PROJECT Jhabua Power Ltd. (JPL) has obtained Environmental clearance for 1x600 MW coal based TPP (Phase 1) from MoEF, New Delhi in 2010 Vide F.No J - 13012/105/2008 IA.II (T) letter dated 17th February, 2010 (Annexure 5). The project is under advance construction phase. Compliance of conditions stipulated in EC letter is being submitted to the respective authorities on regular basis. (Receipt of Compliance Report submission is being enclosed as Annexure 6) Project has received Consent to Establish from MPPCB vide letter no. 11425/ TS/ MPPCB/2010 dated 15.12.10 (Annexure 7). Now, considering the power scenario in the State of Madhya Pradesh, Jhabua Power Limited has proposed further Expansion by installation of 1X660 MW coal based Super Critical TPP (Phase - 2) in villages Barela and Gorakhpur, District Seoni, Madhya Pradesh. Environmental friendly ‘Super-Critical Technology’ has been proposed for the proposed expansion project & the total Power generation Capacity will befrom 600 MW to 1200 MW. Screening Category As per EIA Notification, September, 2006 & as amended on 1st December, 2009, this project falls under Project Activity ‘1(d)’ & Category A, therefore it’s necessary to have Environmental Clearance for the project from Ministry of Environment & Forest, New Delhi. Table 1.1 Dateline/Milestones of process of EC for the project S.NO

PROCESS OF EC IN MoEF

DATE

1.

Date of Application Submitted

6-06-2011

2.

Date of ToR Presentation

5-07-2011

3.

Date of ToR Letter Issued

6-09-2011

4

Date of submission of Public Hearing documents in CECB

29-09-2011

7

Date of Public Hearing

22-11-2011

M/s. Jhabua Power Ltd.

3

J.M.Environet Pvt. Ltd.

Expansion by addition of 1 x 660 MW Coal Based Super Critical TPP (Phase - 2) At Villages Barela and Gorakhpur, Tehsil Ghansore, District Seoni, Madhya Pradesh Final EIA/EMP Report

1.2.2

ABOUT THE PROJECT PROPONENT AVANTHA GROUP has promoted Jhabua Power Ltd. (JPL), to develop and execute coal based thermal power plant in Seoni District, Madhya Pradesh State. The group operates in 8 countries, with an annual turnover exceeding 3.5 billion US dollars, and employs over 20,000 people. It is represented in India and abroad by over 50 different companies and has over 80 manufacturing plants. Crompton Greaves Limited and Ballarpur Industries Limited (BILT) are some of the very well known major companies from the group.

1.3

BRIEF DESCRIPTION OF THE NATURE OF SITE, LOCATION OF THE PROJECT & IMPORTANCE TO THE COUNTRY & REGION The proposed project “expansion by addition of 1×660 MW Coal based Super Critical TPP (Phase II) will come up at villages Barela and Gorakhpur, Tehsil Ghansore, District Seoni, Madhya Pradesh. Table No. – 1.2 Salient Features of the Project

M/s. Jhabua Power Ltd.

4

J.M.Environet Pvt. Ltd.

Expansion by addition of 1 x 660 MW Coal Based Super Critical TPP (Phase - 2) At Villages Barela and Gorakhpur, Tehsil Ghansore, District Seoni, Madhya Pradesh Final EIA/EMP Report

S. No. 1.

Particulars

Details

Project Name

Expansion by addition of 1 x 660 MW Coal Based Super Critical TPP (Phase - 2)

2.

Location Villages

Barela & Gorakhpur

Tehsil

Ghansore

District

Seoni

State

Madhya Pradesh

Geographical Co-ordinates: Latitude- 220 43’ 40”N to 220 44’ 20’’ N & Longitude- 790 54’35” E to 790 55’ 35’’ E Toposheet No. 3.

55 N/14

Environmental Settings of the area Nearest

National NH-7, 18 km in NW direction,

Highway/State Highway

SH – 40, 8 km in SSE direction

Nearest Railway Station

Binaiki R.S. 1km in SW direction

Nearest Airport

Jabalpur, 50 km in NNE direction

Nearest Village

Gorakhpur , 0.6 km in NE direction

Nearest Town

Ghansore, 8.5 km in SSE direction

Nearest Water bodies

Patwara River, 6.5 km in WSW direction Bhagori River ,5.0 km in ESE direction Temur River, 6.5 km in West direction Paryat River 3.0 Km in WSW direction Gadheri River 4.5 Km in WSW direction

M/s. Jhabua Power Ltd.

5

J.M.Environet Pvt. Ltd.

Expansion by addition of 1 x 660 MW Coal Based Super Critical TPP (Phase - 2) At Villages Barela and Gorakhpur, Tehsil Ghansore, District Seoni, Madhya Pradesh Final EIA/EMP Report

Eco

sensitive

Zone No Eco sensitive Zone viz. National Park, Wildlife Sanctuary,

(National Part, Wildlife Biosphere reserve wildlife corridors falling with the 10 km Sanctuary,

Biosphere radius of the project site.

reserve

wildlife The following reserve forests (R.F.) are falling within 10 km

corridors etc.)

radius from the project site:

Within 10 km radius of the project site.

S. No.

Name of RF

Distance from Project boundary

Direction from Project Boundary

1.

Roto Reserve forest

3 km

N to SE

2.

Barwakchhar Reserve forest

7.5 km

N to NE

3.

Katori Reserve forest

9 km

NW

4.

Dhoma Reserve forest

3 km

NW

5.

Diwara Reserve forest

4.7 km

NW

6.

Ghansor Reserve forest

7.5 km

S

7.

Bhattekhari Reserve forest

1.5 km

WNW to SW

8.

Bichhua Reserve forest

3.5 km

ESE

9.

Jaitpur Reserve Forest

8.0 km

SW

10.

Barela Reserve forest

0.0 Km.

SE

11.

Partapgarh P. F.

8.0 Km.

ESE)

Source: SOI Toposheet

Historical

& No Historical & Archeological site falling within 10 km

Archeological Important radius of the project site. Place 4.

Project Requirement Land Requirement

Land requirement for Phase 1:

406.0 acre

Land requirement for Phase 2:

385.79 acre

Total Land requirement

M/s. Jhabua Power Ltd.

6

:

791.79 acre

J.M.Environet Pvt. Ltd.

Expansion by addition of 1 x 660 MW Coal Based Super Critical TPP (Phase - 2) At Villages Barela and Gorakhpur, Tehsil Ghansore, District Seoni, Madhya Pradesh Final EIA/EMP Report

Project Cost Details

Project cost for Phase 1: 2900 Crore Project cost for Phase 2: Rs. 3500 Crore Total Project cost:

Rs. 6400 Crore

Cost for EMP

Capital Cost for EMP (Phase 1): Rs 181.5 Crore

 Capital Cost for EMP

Capital Cost for EMP (Phase 2): Rs 193.0 Crore Total Capital Cost for EMP: Rs. 372.07 Crores

 Recurring

Cost/ Recurring Cost/ annum (Phase-1): Rs. 9.05 Crores/ annum

annum

Recurring Cost/ annum (Phase-2): Rs 9.50 Crore) Total Recurring Cost for EMP: Rs 18.55 Crores/annum

Water Requirement

Water requirement for Phase 1: 23 MCM/ annum Water requirement for Phase 2: 15.33 MCM/ annum Total Water requirement:

38.33 MCM/ annum

Source: Bargi Reservoir (Permission for 23 MCM/ annum has been obtained from Department of Water Resources, MP vide letter no. C.P.C.B./31/Tak/State Govt. – 162/08/86 dated 06.02.09. Copy enclosed as Annexure 3A. An agreement has been signed between Narmada Valley Development Authority and M/s Jhabua Power Limited on 21’st Feb. 2011 for 16.88 MCM/ annum of water withdrawal from Bargi Reservior (Copy enclosed as Annexure – 3B) Manpower

Manpower requirement for Phase 1: 300 Persons

Requirement

Manpower requirement for Phase 2: 150 Persons Total Manpower requirement:

Coal Requirement

450 Persons

Coal requirement for Phase 1: 3.2 MTPA Coal requirement for Phase 2: 3.62 MTPA Total Coal requirement:

6.82 MTPA

Source:  SECL/MCL mines (Letter of Assurance for Coal Linkage are enclosed as Annexure -4) Source: Prefeasibility Report & Site Visit Report

M/s. Jhabua Power Ltd.

7

J.M.Environet Pvt. Ltd.

Expansion by addition of 1 x 660 MW Coal Based Super Critical TPP (Phase - 2) At Villages Barela and Gorakhpur, Tehsil Ghansore, District Seoni, Madhya Pradesh Final EIA/EMP Report

1.3.1

TOPOSHEET MAP

Figure no. 1.1 (Environmental Setting of the study area)

M/s. Jhabua Power Ltd.

8

J.M.Environet Pvt. Ltd.

Expansion by addition of 1 x 660 MW Coal Based Super Critical TPP (Phase - 2) At Villages Barela and Gorakhpur, Tehsil Ghansore, District Seoni, Madhya Pradesh Final EIA/EMP Report

1.3.2

Importance to the Country & Region Energy is one of the major inputs for economic development of any country. In the case of the developing countries like India the energy sector assumes a critical importance in view of the ever-increasing energy needs requiring huge investments to meet them. The electricity sector in India had an installed capacity of 207.85 Gigawatt (GW) as of September 2012. India currently suffers from a major shortage of electricity generation capacity, even though it is the world's fourth largest energy consumer after United States, China and Russia. The 17th electric power survey of India report claims: 

Over 2010–11, India's industrial demand accounted for 35% of electrical power requirement, domestic household use accounted for 28%, agriculture 21%, commercial 9%, public lighting and other miscellaneous applications accounted for the rest.



The electrical energy demand for 2016–17 is expected to be at least 1392 Tera Watt Hours, with a peak electric demand of 218 GW.



The electrical energy demand for 2021–22 is expected to be at least 1915 Tera Watt Hours, with a peak electric demand of 298 GW.

Hence, looking at the above power scenario the upcoming project will be beneficial for the country as well as for the region. 1.3.3

Site Selection The project activity is an expansion activity (Phase-2) proposed within the existing premises of upcoming thermal Power Plant (Phase-1) for which Environment Clearance has been granted. Initially many sites were considered for the Phase-1 project and this site at village Barela & Grakhpur was recommended by the MoEF. The expansion project has been considered in the existing premises looking at the various facilities already available or proposed in Phase-1. The project site has following advantages: 

Availability of fuel i.e, coal which will be obtained from SECL/MCL and the system planned for coal transportation and railway siding for phase 1 will be used for Phase 2 with certain necessary modifications.

M/s. Jhabua Power Ltd.

9

J.M.Environet Pvt. Ltd.

Expansion by addition of 1 x 660 MW Coal Based Super Critical TPP (Phase - 2) At Villages Barela and Gorakhpur, Tehsil Ghansore, District Seoni, Madhya Pradesh Final EIA/EMP Report



Availability of adequate water, which will be obtained from Bargi Reservoir on river Narmada located at about 13 km from the site.



Availability of adequate land for locating the plant with approach roads



Power evacuation from the site is available which can be made through 400 KV Sub Station either at Seoni or at Jabalpur



Suitability of land from topography and geological aspects



The site is more than 500 m from railway line, HFL of river & State highway and the site is not falling in sensitive zone such as Historical monuments, Wild Life Sanctuaries, National parks etc.

1.4

SCOPE OF THE STUDY The project activity was considered before the Expert Appraisal Committee (T) for its First technical presentation (ToR) on 18th Oct, 2010. The EAC has suggested Terms of References (ToR) for preparation of the Environmental Impact Assessment (EIA) Report and Environmental Management Plan (EMP) vide its File No. J13012/63/2010 - IA. II (T) & Letter dated 8th December, 2010 & 6th September, 2011. The Final EIA/EMP Report has been prepared incorporating all the prescribed ToR points by MoEF along with the issues raised and action plan for the issues raised during the public hearing.

M/s. Jhabua Power Ltd.

10

J.M.Environet Pvt. Ltd.

Expansion by addition of 1 x 660 MW Coal Based Super Critical TPP (Phase - 2)At Villages Barela and Gorakhpur, Tehsil Ghansore, District Seoni, Madhya Pradesh Final EIA/EMP Report

CHAPTER–II PROCESS DESCRIPTION 2.1

TYPE AND NEED OF THE PROJECT

2.1.1

Type of the Project Jhabua Power Limited has obtained Environmental clearance for 1 x 600 MW coal based TPP (Phase 1) in villages Barela and Gorakhpur, District Seoni, Madhya Pradesh from Ministry of Environment and Forest, New Delhi in 2010 Vide F. No. J 13012/105/2008 - IA.II (T) letter dated 17th February, 2010. (A Copy of EC Letter is enclosed as Annexure-5) Now, considering the power scenario in the State of Madhya Pradesh, Jhabua Power Limited is proposing Expansion by installation of 1X660 MW Coal based Super critical TPP (Phase - 2) in villages Barela and Gorakhpur, District Seoni, Madhya Pradesh. As per EIA Notification, September, 2006 & as amended on 1st December, 2009, this project falls under Category “A” S. No. ‘1d’ (Power Generation), hence Environmental Clearance from Ministry of Environment & Forest, New Delhi is necessary.

2.1.2

Need for the Project

2.1.2.1

Power Scenario in the Country As per the “5th National Power Plan (2002-2012)” prepared by CEA, a need based installed capacity of the order of 2,12,000 MW is required by the end of 11th plan based on demand projections of 17th Electric Power Survey and a system reliability level of Loss of Load Probability less than 1% of the country. The primary resources for electric power generation are water, fossil fuel (coal, lignite, oil and natural gas) and nuclear energy. These would continue to serve as major sources of power generation in the long run, though various forms of renewable sources viz. wind, bio-mass, tides etc. will also contribute to meeting the demand. Based on the report of the Working Group of Power constituted by Planning Commission, a capacity addition of 41,110 MW is targeted in 10th plan comprising 14,393 MW of Hydro, 25,417 MW of thermal and 1,300 MW of nuclear. Out of the total thermal capacity of 25,417 MW, the coal/lignite based capacity shall be 20,053 MW.

M/s. Jhabua Power Ltd.

11

J.M.Environet Pvt. Ltd.

Expansion by addition of 1 x 660 MW Coal Based Super Critical TPP (Phase - 2)At Villages Barela and Gorakhpur, Tehsil Ghansore, District Seoni, Madhya Pradesh Final EIA/EMP Report

For 11th Plan, CEA has identified a capacity addition requirement of 67,439 MW. The 11th Plan program is comparatively large so as to provide not only for normal growth during the 11th Plan period but also to compensate for any shortfall in the capacity addition during the 10th plan period. 2.1.2.2

Power Development Scenario Beyond 11th Plan (2012-20) The Indian power system requirement has been assessed to need a hydro power and thermal/nuclear power mix in the ration of 40:60 for flexibility in system operation depending on typical load pattern. The motion to achieve this mix and to accelerate the hydro electric power generation of 50, 000 MW has been already initiated by Government of India (GoI). CEA has identified new hydro schemes aggregating to a capacity of 30,000 MW for yielding benefits during the 12th Plan period (2012-2017). These schemes have been identified based on their present status as available with the CEA. Nuclear Power Corporation has planned to add nuclear power projects aggregating to 12,000 MW to be commissioned in year 2012-2017. With the capacity additional of 21,180 achieved during 10th Plan and 78,578 MW assessed as required during the 11th plan, it is expected that “Power to All” would be achieved by 2012. A tentative capacity addition of 82,200 MW has been envisaged for the 12th plan. This comprises of 30,000 MW hydro, 40,200 MW thermal and 11000-13000 MW of Nuclear Power Plant. Table No. 2.1 Actual Power Supply Position, 2010-2011 (March, 11)

S. L. N

Region

Thermal

Total

COAL

GAS

DIESEL

Nuclear

Hydro

R.E.S

(Renew)

(Minre)

Total

1

NORTHERN

23620.00

3884.76

12.99

27517.75

1620.00

13622.75

2777.32

45537.82

2

WESTERN

31080.50

7903.81

17.48

39001.79

1840.00

7447.50

4918.28

53207.57

3

SOUTHERN

19382.50

4690.78

939.32

25012.60

1100.00

11299.03

8517.55

45929.18

4

EASTERN

18235.38

190.00

17.20

18442.58

0.00

3882.12

344.41

22669.11

5

N.EASTERN

60.00

787.00

142.74

989.74

0.00

1116.00

223.32

2329.06

6

ISLANDS

0.00

0.00

70.02

70.02

0.00

0.00

6.10

76.12

ALL INDIA

92378.38

17456.35

1199.75

111034.48

4560.00

37367.40

16786.98

169748.8 (AS ON 31.10.2010)

MARCH11*

93918.38

M/s. Jhabua Power Ltd.

17706.35

1199.75

112824.48

12

4780.00

37567.40

18454.52

173626.40

J.M.Environet Pvt. Ltd.

Expansion by addition of 1 x 660 MW Coal Based Super Critical TPP (Phase - 2)At Villages Barela and Gorakhpur, Tehsil Ghansore, District Seoni, Madhya Pradesh Final EIA/EMP Report

Table No. 2.2 Energy Requirement of the Indian Regions REGION

ENERGY

DEFICIT

REQUIREMENT (MU)

PEAK

DEFICIT %

DEMAND (MW)

NORTHERN

22,168

-4.7

34,856

-8.8

WESTERN

25,400

-12.3

40,798

-14.7

SOUTHERN

23,037

-6.0

33,225

-6.3

EASTERN

8,076

-4.4

14,528

-11.4

NORTH EASTERN

829

-6.5

1,67

6.9

ALL INDIA

79,510

-7.5

125,077

-10.3

2.1.2.3

Power Demand Scenario in Madhya Pradesh The Madhya Pradesh state peak power load and the energy requirement forecast of the CEA’s 17th EPS is shown below:

M/s. Jhabua Power Ltd.

13

J.M.Environet Pvt. Ltd.

Expansion by addition of 1 x 660 MW Coal Based Super Critical TPP (Phase - 2)At Villages Barela and Gorakhpur, Tehsil Ghansore, District Seoni, Madhya Pradesh Final EIA/EMP Report

Table No. 2.3 (A) period

9TH PLAN END 2002-03 2003-04 2004-05 2005-06 2006-07 2007-08 2008-09 2009-10 APR-DEC, 2010 DEC,2010

ACTUAL POWER SUPPLY POSITION Peak Energy Energy Deficit/surplus Requirment Availability (%) (MU) (MU) -21.6 31013 26233

Peak demand (MW) 5683

Peak Met (MW) 4457

Peak eficit/surplus (MW) -1226

5869 6158 5944 6558 8090 7200 7564 7,490 8,690

4157 4799 4846 5136 6404 6436 6810 6,415 7,650

-1712 -1359 -1098 -1422 -1686 -764 -754 -1,075 -1,040

-29.2 -22.1 -18.5 -21.7 -20.8 -10.6 -10.0 -14.4 -12.0

31705 32744 34810 36846 38710 41560 42054 43,179 33,773

8,690

7,175

-1,515

-17.4

5,090

Energy Deficit/Surplus (mu) -4780

Energy Deficit/Surplus (%) -15.4

26493 28317 30097 31619 32834 35700 34841 34,973 27,114

-5212 -4327 -4713 -5227 -5876 -5860 -7213 -8,206 -6,659

-16.4 -13.2 -13.5 -14.2 -15.2 -14.1 -17.2 -19.0 -19.7

3,911

-1,179

-23.2

NOTE: - peak demand – 8129 MW, Energy requirement – 47011 MU for the year 2010-2011 (as per 17th eps report) occurrence of peak as per actual power supply position in the months(S) – December & February. Table No. 2.3 (B) LIKELY POWER SUPPLY POSITION AT THE END OF 2011-12*(DEMAND AS PER 17TH EPS) period

2011-12

Peak demand (MW) 8462

Peak Met (MW) 7555

Peak eficit/surplus (MW) -907

Peak Deficit/surplus (%) -10.7

Energy Requirment (MU) 49338

Energy Availability (MU) 44085

Energy Deficit/Surplus (mu) -5253

*Peak and Energy availability from all IPPs to be commissioned during 11th Plan are taken in the respective state. M/s. Jhabua Power Ltd.

14

J.M.Environet Pvt. Ltd.

Energy Deficit/Surplus (%) -10.6

Expansion by addition of 1 x 660 MW Coal Based Super Critical TPP (Phase - 2)At Villages Barela and Gorakhpur, Tehsil Ghansore, District Seoni, Madhya Pradesh Final EIA/EMP Report

2.1.2.4

Overall Madhya Pradesh Power Load And Energy Requirement Details

200708

200809

200910

201011

201112

201617

202122

Peak Load (MW)

7206

7501

7809

8129

8462

11772

16129

Energy Requirement (MkWh)

40666

42680

44793

47011

49338

70445

98987

Considering the above power scenario in the State of Madhya Pradesh, the need for Expansion of Power generation capacity from 600 to 1260 MW ( By installation of 1X660 MW, Phase - 2) power plant by M/s Jhabua Power Limited is justified.

M/s. Jhabua Power Ltd.

15

J.M.Environet Pvt. Ltd.

Expansion by addition of 1 x 660 MW Coal Based Super Critical TPP (Phase - 2)At Villages Barela and Gorakhpur, Tehsil Ghansore, District Seoni, Madhya Pradesh Final EIA/EMP Report

2.2

Location Map of the Project Site

Figure No: 2.1: Location Map of the Project Site M/s. Jhabua Power Ltd.

16

J.M.Environet Pvt. Ltd.

Expansion by addition of 1 x 660 MW Coal Based Super Critical TPP (Phase - 2)At Villages Barela and Gorakhpur, Tehsil Ghansore, District Seoni, Madhya Pradesh Final EIA/EMP Report

2.2.1

View of Construction Site of Phase-I TPP

STACK (Chimney)

BOILER PROPER

WATER TREATMENT PLANT

ESP Arial View

IDCT

CHP Conveyer

Figure No. 2.2: View of Construction Site of Phase-I TPP

M/s. Jhabua Power Ltd.

17

J.M.Environet Pvt. Ltd.

Expansion by addition of 1 x 660 MW Coal Based Super Critical TPP (Phase - 2)At Villages Barela and Gorakhpur, Tehsil Ghansore, District Seoni, Madhya Pradesh Final EIA/EMP Report

2.2.2

Plant Layout Layout of the proposed power plant shall be optimized considering the space requirement for all the equipments, systems, buildings and structures, including railway marshalling yard and ash disposal area. Following facilities shall be considered during preparation of the layout of proposed power plant. Ash pond area marked on Toposheet is shown in Figure no. 1.1 in Chapter-1 Introduction. 

Coal storage yard for 20 days storage at site.



Ash disposal area.



Raw water supply and storage facilities.



Railway Siding and Marshalling Yard.



Approach road to the power plant from main road.



Availability of adequate space for fabrication / construction equipment.

The power plant shall comprise of two Boilers and two steam turbine generator (STG) with the required auxiliaries of various units and equipments. The plant layout is given in figure no. 2.3: Steam Generator The steam generator will be once through type, water tube, direct pulverised coal fired, balanced draft furnace, single reheat, radiant, wet bottom type, suitable for outdoor installation, top supported and designed for firing 100% Indian coal rated to deliver about 2100 TPH of superheated steam at 250 bar (a), 568°C (±5°) when supplied with feed water at a temperature of 290°C at the economiser inlet under BMCR condition. Electrostatic Precipitator The proposed steam-generating unit will be provided with Electro-static Precipitator. The precipitator will have four parallel gas paths, any of which can be isolated for maintenance when required, keeping the other paths in operation. The ESP will be such that the outlet flue gas dust content does not exceed 50 mg/Nm3 at 100% TMCR even when 1 field is out of service.

M/s. Jhabua Power Ltd.

18

J.M.Environet Pvt. Ltd.

Expansion by addition of 1 x 660 MW Coal Based Super Critical TPP (Phase - 2)At Villages Barela and Gorakhpur, Tehsil Ghansore, District Seoni, Madhya Pradesh Final EIA/EMP Report

Design criteria i)

Number of gas paths per boiler Four Nos. gas streams housed in four independent casings.

ii)

Capacity of each section 25% of BMCR.

iii)

Capacity of one section with one stream out of service 30% of BMCR.

vi)

Velocity of flue gas through ESP 1.0 m / sec (Max).

v)

Type of control Microprocessor based controls with pulse optimisation and intermittent charging, features.

CHIMNEY One (1) Bi-flue concrete chimney of 275 m height common for both the units has been considered in accordance with the guidelines given by the MoEF. The chimney will include openings sized and located to coordinate with the presently specified configuration of ESP and also be easily adapted to a future configuration that includes flue gas desulphurization equipment which will be located in the flue gas stream between the ESP and the chimney. STEAM GENERATOR C&I Steam generator will be provided with the following control instrument features proper and safe to facilitate boiler operation. 

Furnace safeguard supervisory system (FSSS) will be provided for the safe operation of



the Boiler at all operating conditions including startups in compliance with NFPA standard.



FSSS facilitates remote operations of high energy arc igniters, oil guns & pulveriser. It takes care of Boiler trip conditions as specified during boiler operation



Variable frequency drive for ID Fan control.



Analytical measurement for flue gas, steam & water.



Modern Automatic co-coordinated distributed control system with DCS will be provided for automatic control of Boiler and auxiliaries.

M/s. Jhabua Power Ltd.

19

J.M.Environet Pvt. Ltd.

Expansion by addition of 1 x 660 MW Coal Based Super Critical TPP (Phase - 2)At Villages Barela and Gorakhpur, Tehsil Ghansore, District Seoni, Madhya Pradesh Final EIA/EMP Report

STEAM TURBINE The steam turbine will be of 3000 rpm, tandem compound, single reheat, regenerative, condensing, three (3) cylinder machine with eight (8) uncontrolled extractions for regenerative feed water heating. The main steam parameters at 100% TMCR load will be 242.23 bars at 565°C before emergency stop valves of HP turbine and reheat steam parameters of 49.34 bars and 593°C at inlet to IP turbine and the condenser pressure will be of 0.1 bars. At turbine valve wide open (VWO) condition the turbo-generator set will be able to operate continuously with a throttle steam flow of about 105% TMCR condition. The steam turbine generator will be suitable for tropical climate prevailing in India and indoor installations on reinforced concrete top deck preferably supported on vibration isolation system consisting of steel helical springs and visco dampers. CONDENSING EQUIPMENT Single pass surface condenser capable of maintaining the required vacuum while condensing steam at the maximum rating of the turbine will be provided. Other recoverable steam and condensate will also be routed to the condenser shells. The steam will be condensed in the condenser by circulating water passing through the condenser tubes. The condenser arrangement will be such that on-load maintenance of one half of the condenser at a time is possible by isolating the same from cooling water inlet and outlet sides. The condenser will be of divided water box design with rolled steel construction of body and water chamber. Tubes in the condensing zone and in the air cooling zone will be of Stainless Steel to SA 249 TP 304. Tube sheet will be of Carbon steel to SA 516 Gr. 70 or equivalent. The condensers will have integrated air cooling zone and it should be designed so as to accept 60% quantity of steam during turbine HP and LP bypass operation without any undue vibration, thermal stress etc. The condenser axis will be at right angle to the turbo-generator axis. CONDENSER AIR EVACUATION SYSTEM Air evacuation systems commonly used for condensers are Steam ejectors or mechanical vacuum pumps. With increase in unit rating and steam conditions, it is uneconomical to provide large quantities of relatively low conditions steam to steam jet ejector. The capacity of vacuum pump rises steeply with increase in condenser back pressure than the ejector and hence when the air leakage in condenser

M/s. Jhabua Power Ltd.

20

J.M.Environet Pvt. Ltd.

Expansion by addition of 1 x 660 MW Coal Based Super Critical TPP (Phase - 2)At Villages Barela and Gorakhpur, Tehsil Ghansore, District Seoni, Madhya Pradesh Final EIA/EMP Report

increases more than its design value, the vacuum pump can handle more air than ejectors of the same capacity. Based on the operating conditions, operation flexibility, layout convenience, system reliability and economics, the vacuum pumps are selected for condenser Air evacuation system. BOILER FEED PUMPS AND DRIVES For 660 MW T.G. unit, two (2) steam turbine driven boiler feed pumps of 50% capacity have been adopted for start-up purpose & one 50% capacity motor driven boiler feed pump is provided as a standard feature. This is as per international design practice for the 500 MW/660 MW T.G. units rating adopted in Europe, USA & China & other countries. DEAERATING HEATER AND CLOSED HEATERS The proposed unit will be provided with a variable pressure type deaerator with a feed water tank of adequate capacity. Vent condenser will be provided with the deaerator to minimize wastage of steam. The deaerator will be spray or spray-cumtray type and will be designed to deaerate all the incoming condensate and drain flows to keep the oxygen content of the condensate below the permissible limit. CONDENSATE EXTRACTION PUMPS The proposed unit will have three (3) x 50% capacity (2W + 1S) condensate extraction pumps, which will take suction from condenser hot well and discharge through common supply line to the Deaerator. The condensate extraction pumps will be vertical motor driven centrifugal can-type, multistage, with double suction first stage impellers. The pumps will be located indoors near the condenser with the pump base plates at ground floor and will be arranged for below ground suction from the condenser hot well. Connections for condensate supply to the following major services will be tapped off from this condensate discharge header: 

LP bypass desuperheating spray



Turbine exhaust hood spray



Gland sealing system desuperheating spray

M/s. Jhabua Power Ltd.

21

J.M.Environet Pvt. Ltd.

Expansion by addition of 1 x 660 MW Coal Based Super Critical TPP (Phase - 2)At Villages Barela and Gorakhpur, Tehsil Ghansore, District Seoni, Madhya Pradesh Final EIA/EMP Report

COAL HANDLING SYSTEM This section covers the provisions that will be made for the coal handling system for the 1 x 660 MW extension units which will be integrated with CHS of phase-1. It covers proposed facilities for receipt of coal by BOX-N wagons, unloading, crushing, conveying coal up to the steam generator bunkers or stockyard, reclaiming from the stockyard and conveying same to steam generator bunkers. MECHANICAL AUXILIARY SYSTEM Machines Auxiliary System consist Cooling water system, Auxiliary Cooling Water (ACW) and Closed Cooling Water (CCW), Fire detection and Protection System, Fuel Oil System, Compressor Air System, Turbine Oil Purification System, Chemical Feed System, Elevators, Cranes & Hoisting Equipment, Chemical Laboratory, Workshop Equipment, Air Conditioning System, Ventilation System, Thermal Insulation and Painting.

M/s. Jhabua Power Ltd.

22

J.M.Environet Pvt. Ltd.

Expansion by addition of 1 x 660 MW Coal Based Super Critical TPP (Phase - 2)At Villages Barela and Gorakhpur, Tehsil Ghansore, District Seoni, Madhya Pradesh Final EIA/EMP Report

Figure No. 2.3: Plant Layout

M/s. Jhabua Power Ltd.

23

J.M.Environet Pvt. Ltd.

Expansion by addition of 1 x 660 MW Coal Based Super Critical TPP (Phase - 2)At Villages Barela and Gorakhpur, Tehsil Ghansore, District Seoni, Madhya Pradesh Final EIA/EMP Report

2.3

EQUIREMENTS FOR THE PROJECT

2.3.1

Land Requirement Total land requirement is 791.8 Acres for (Phase-I and Phase-II). Out of which 406 Acre land is for Phase-I and remaining 385.8 Acre is for Phase-II TPP. Out of total land required, 100 % land has been acquired for Phase I & Phase II. The break-up of the land for the project is given in Table below: Table No. – 2.4 (A) UNIT WISE LAND REQUIREMENT

S. No.

Ph-I

Ph-II

Total

(1x600 MW) in Acre

(1x600 MW) in Acre

(2x600 MW) in Acre

Unit

1

Boiler, TG, Transformer yard

13

15

28

2

Coal handling plant

65

32

97

3

Raw water reservoir

25

30

55

4

Water system (water treatment plant, STP, CT, clarification plant)

19

11

30

5

400 kV switch yard

25

30

55

6

Ash Handling System

2

2

4

7

Construction and permanent store

5

11

16

8

Miscellaneous Station Facilities (Incl. adm. Building, workshop, fire station, canteen, lay down)

2.5

2.5

5

9

Road

13

16

29

10

Ash disposal

90

95

185

11

Colony / township

12.5

14.3

26.8

12

Landscaping and greenbelt

134

127

261

406

385.8

791.8

Total Source: Detailed Project Report

M/s. Jhabua Power Ltd.

24

J.M.Environet Pvt. Ltd.

Expansion by addition of 1 x 660 MW Coal Based Super Critical TPP (Phase - 2)At Villages Barela and Gorakhpur, Tehsil Ghansore, District Seoni, Madhya Pradesh Final EIA/EMP Report

Table No. – 2.4 (B) UNIT WISE LAND REQUIREMENT Type of

2.3.2

Phase - I

Phase - II

TOTAL

Land

Required

Acquired

Required

Acquired

Required

Acquired

Private (including Tribal)

187.04

187.04

376.21

376.21

563.25

563.25

Govt.

218.96

218.96

0

0

218.96

218.96

Forest

0

0

9.58

9.58

9.58

9.58

TOTAL

406

406

385.79

384.81

791.79

790.81

Water The total water requirement for the proposed expansion project (Phase 2) is estimated to be 15.33 MCM. The same will be sourced from Bargi Reservoir. The withdrawal point will be near village Gadaghat located approx. 10.0 km away from the site. Map showing the water intake point is given below:

M/s. Jhabua Power Ltd.

25

J.M.Environet Pvt. Ltd.

Expansion by addition of 1 x 660 MW Coal Based Super Critical TPP (Phase - 2)At Villages Barela and Gorakhpur, Tehsil Ghansore, District Seoni, Madhya Pradesh Final EIA/EMP Report

Figure no. 2.4 (Image showing the distance of water intake point of Bargi Dam Reservoir from the Project site)

M/s. Jhabua Power Ltd.

26

J.M.Environet Pvt. Ltd.

Expansion by addition of 1 x 660 MW Coal Based Super Critical TPP (Phase - 2)At Villages Barela and Gorakhpur, Tehsil Ghansore, District Seoni, Madhya Pradesh Final EIA/EMP Report

Permission for 23 MCM/annum water withdrawal for Phase -1, has been obtained from Department of Water Resources, MP vide letter no. C.P.C.B./31/Tak/State Govt. – 162/08/86 dated 06.02.09. (Copy enclosed as Annexure 3A. An agreement has been signed between Narmada Valley Development Authority and M/s Jhabua Power Limited on 21’st Feb. 2011 for 16.88 MCM/ annum of water withdrawal for Phase -2 from Bargi Reservior. (Copy enclosed as Annexure –3B) Raw water from Bargi Reservoir will be pumped to raw water reservoir of 15 days storage capacity, located in plant area. Total land requirement for Pipeline laying is mentioned below: Table No. 2.5 LAND REQUIREMENT FOR PIPELINE LAYING Type of Land

Required (in Acres)

Available

Balance

Forest

8.74734

0

8.74734

Govt.

1.339282

0

1.339282

Pvt.

13.526254

0

13.526254

Total

23.612876

0

23.612876

The Raw water Storage system consists of the existing plant reservoir which will be used for storing the raw water required for operation of extension unit. Two (1W+1S) vertical turbine type plant make up pumps are provided in Phase-1 of the project. An additional pump of equal capacity will be provided in Phase-2. The standby pump provided in phase-1 will act as a common standby for both the phases. Plant make up pumps feed raw water from the raw water reservoir in the plant to the solid contact clarifier. The raw water will be pumped from the reservoir to the clarifier where raw water will be clarified to remove suspended solids and colloidal particles. Clarified water would be supplied as make-up water in the cooling tower basin and filtration plant. Filtered water will be required for potable use, air conditioning plant and DM plant feed. The raw water reservoir and pump house, pre-treatment /filtration plant will be located adjacent to the water treatment plant area. The raw water storage reservoir has been sized for meeting 15 days water requirement of the plant. The water balance for Phase 2 is given bellow: The details of water balance is given in the flow diagram below::

M/s. Jhabua Power Ltd.

27

J.M.Environet Pvt. Ltd.

Expansion by addition of 1 x 660 MW Coal Based Super Critical TPP (Phase - 2)At Villages Barela and Gorakhpur, Tehsil Ghansore, District Seoni, Madhya Pradesh Final EIA/EMP Report

Figure No.2.5: Water Balance Diagram

M/s. Jhabua Power Ltd.

28

J.M.Environet Pvt. Ltd.

Expansion by addition of 1 x 660 MW Coal Based Super Critical TPP (Phase - 2)

Final EIA/EMP Report

At Villages Barela and Gorakhpur, Tehsil Ghansore, District Seoni (Madhya Pradesh)

2.3.3

Coal Requirement 3.62 MTPA of coal will be required for the proposed expansion project. The coal shall have Calorific Value of 3150 Kcal/kg with ash content of 45.6%. Thesulphur content is 0.5%. The coal will be transported from MCL/SECL mines to the power plant in dedicated wagons through railway. Documents for coal linkage assurance are annexed with the Final EIA/EMP Report as Annexure 4. Analysis of coal is presented in bellow Table: Table-2.6 ANALYSIS OF COAL S. No.

Characteristics

Percentage (%)

1. Moisture (as received basis)

10-16

2. Ash

32-48

3. Volatile matter

19-24

4. Fixed carbon

19-32

Ultimate Analysis 5. Carbon

30-42

6. Hydrogen

2.3-2.75

7. Nitrogen

0.6-0.9

8. Sulphur

0.5

9. Oxygen

5.19-8.9

10. GCV (Kcal/kg)

3000-4000

Source : DPR

Coal will be transported from the MCL/ SECL mines by railway line. From MCL/ SECL mines the coal will be transported up to Jabalpur via Katni from where it will be transported up to project site by Jabalpur – Gondia railway line. The route and mode of transportation of the coal will be kept as that of Phase-1. 2.3.3.1

Fuel Oil The requirement of furnace oil is proposed to be sourced from the open market. JPL proposes to use a combination of Heavy fuel oil and Light Oil. The first will be provided as secondary fuel for pulverized coal flame stabilization at low loads. Light Oil will be provided as secondary fuel for starting purpose. The system shall be common for both the units.

M/s. Jhabua Power Ltd.

29

J.M.Environet Pvt. Ltd.

Expansion by addition of 1 x 660 MW Coal Based Super Critical TPP (Phase - 2)

Final EIA/EMP Report

At Villages Barela and Gorakhpur, Tehsil Ghansore, District Seoni (Madhya Pradesh)

The boiler will be designed for cold start-up and initial warm-up using light diesel oil (LDO)/ Heavy Fuel oil (HFO). The annual requirement of Warm-up & start-up fuels LDO/HFO used for cold start up with initial warm up is estimated to be around 2000/16,000 tonnes per annum. The characteristics of the fuel oil and furnace oil are presented in Table 2.7 (A) and Table 2.7 (B) respectively. Table No:-2.7 (A) CHARACTERISTICS OF THE FUEL OIL (LDO Diesel Fuels IS: 1460-1974) S. No.

Parameter

Details

1.

Acidity

Nil

2.

Ash, percent by mass

0.02

3.

Carbon Residue(Remo bottom)

1.50

4.

++ Pour point, Max.

12° C for winter, 21°C for summer

5.

Flash point

66° C

6.

Kinematic viscosity, cs, at 38° C

7.

Sediment percent by mass (max.)

8.

Sulphur content by mass (max.)

1.8 %

9.

Water content percent by volume, Max.

0.25

2.5-15.7 0.1

Source: DPR Table-2.8 (B) CHARACTERISTICS OF FURNACE OIL (IS Specification for Furnace oil Grade HV IS: 1953-1971) S. No.

Parameter

Details

1.

Acidity

Nil

2.

Ash, % by mass

0.1

3.

Gross calorific value

4.

Flash point ,Min.

66°C

5.

Kinematic viscosity in Centristrokes at 50°C, Max.

370

6.

Sediment, %by mass, Max.

0.25

7.

Sulfur, total % by mass, Max.

4.5

8.

Water content, % by mass, Max.

1.0

9500 Kcal/kg

Source:DPR 2.3.4

Manpower Approximate 150 persons would be required for proposed expansion project. Many people from neighbouring villages may get opportunity for employment during construction and operation phase. Indirect employment will be generated during construction phase

M/s. Jhabua Power Ltd.

30

J.M.Environet Pvt. Ltd.

Expansion by addition of 1 x 660 MW Coal Based Super Critical TPP (Phase - 2) At Villages Barela and Gorakhpur, Tehsil Ghansore, District Seoni (Madhya Pradesh)

2.4

Final EIA/EMP Report

TECHNOLOGY & PROCESS DESCRIPTION In thermal power generation, chemical energy of coal is first converted into thermal energy (during combustion), which is then converted into mechanical energy (through a turbine) and finally into electrical energy (through a generator). Figure 2.6 shows the process flow sheet for coal fired thermal power plant. Its raw materials are coal, air and water. The coal travels from the coal handling plant by conveyor belt to the coal bunkers, from where it is fed to the pulverising mills which grind it as fine as face powder. The finely powdered coal mixed with air is then blown into the boiler by a fan where it burns like a gas. The boiler walls are lined with boiler tubes containing high quality demineralised water (known as boiler feed water). The combustion heat released from the coal is absorbed by the boiler tubes and the heat converts the boiler feed water into steam at high pressure and temperature. The steam discharged through nozzles on the turbine blades, makes the turbine rotate. Generator is coupled to the end of the turbine. When the turbine rotates, the electricity is produced in generator, which is passed to the stepup transformer which increases its voltage so that it can be transmitted efficiently over the power line of the grid. The power is evacuated via Switch Yard through a Transmission System.

Fig. No. 2.6 Process Flow Chart

M/s. Jhabua Power Ltd.

31

J.M.Environet Pvt. Ltd.

Expansion by addition of 1 x 660 MW Coal Based Super Critical TPP (Phase - 2)

Final EIA/EMP Report

At Villages Barela and Gorakhpur, Tehsil Ghansore, District Seoni (Madhya Pradesh)

2.4.1

Steam Generator and Accessories Steam Generator The steam generator will be once through type, water tube, direct pulverised coal fired, balanced Final furnace, single reheat, radiant, wet bottom type, suitable for outdoor installation, top supported and designed for firing 100% Indian coal rated to deliver about 2100 TPH of superheated steam at 250 bar(a), 568°C (±5°) when supplied with feed water at a temperature of 290°C at the economiser inlet under BMCR condition. The combustion system will be of pulverised coal firing with Low NOX type coal burners. The firing system will be either corner firing (tangential) or front and opposite wall firing as per the standard design feature of steam generator manufacturer. The steam generator will be designed for continuous satisfactory operation for the specified range of coal without any need for auxiliary fuel for flame stabilisation above minimum load operation. The furnace will be conservatively designed for fuel to burn completely and to avoid any slagging in the furnace and excessive fouling in the super heater sections of the boiler. The design flue gas velocities will be carefully selected to minimise erosion of pressure parts and other vital components on account of ash. The steam generator will be designed in accordance with the latest provisions of Indian Boiler Regulations. The steam generator will be designed to give the maximum efficiency when firing the coal. Capacity of steam generating unit will be so selected as to ensure adequate margin over the requirement of Turbine at valve wide open (VWO), auxiliary steam requirement for soot blowing operation, start-up of the adjacent unit, and derating of the steam generating unit due to prolonged use. The steam generator will be designed to operate with “the HP Heaters out of service” condition (resulting in lower feed water temperature at Economiser inlet) and deliver steam to meet the turbo-generator requirement at base load. Economiser section of the boiler will be non-steaming type. Super heater section will be divided in convection and radiant zones and designed so as to maintain rated steam temperature of 568°C (±5°) at outlet. Main steam attemperation stations with provision for spraying water tapped off from feed water piping will be provided for steam temperature control. Air preheaters of rotary tri sector type will be provided with a set of soot blowers of automatic sequential electrically operated type, arranged for on-load cleaning of the heat transfer surfaces. Inline with the plant operating capability requirements, the

M/s. Jhabua Power Ltd.

32

J.M.Environet Pvt. Ltd.

Expansion by addition of 1 x 660 MW Coal Based Super Critical TPP (Phase - 2) At Villages Barela and Gorakhpur, Tehsil Ghansore, District Seoni (Madhya Pradesh)

Final EIA/EMP Report

steam generator will be designed for both constant as well as sliding pressure operation. Thermal design of steam generator and the selection of materials will be suitable for both the operational modes. Final system of the boiler will be provided with two (2) Forced Final Fans, two(2) Primary Air Fans and two (2) Induced Final Fans with suitable capacity and control arrangement, each independently capable of meeting the requirement at 60% BMCR load. The forced Final fans will control total airflow to boiler and the induced Final fans will control furnace Final of the boiler through automatic control loops. The crushed coal will be received from the coal handling plant through conveyors and stored in the coal bunkers of about 16 hours storage capacity and the same will be fed to the coal pulverisers utilising gravimetric feeders. The pulverised coal will then be distributed to the Low NOx coal burners from each mill for combustion in the furnace of the boiler through coal conveying pipes. It is considered that even with one pulverising coal mill out of service, it will be possible to achieve 100 % BMCR. The steam generating unit will be provided with arrangement for start-up and at low load stabilisation periods when firing coal utilising liquid fuel such as LDO/HFO. The complete boiler will be top supported type and will be provided with all supporting steel structures, platforms, galleries, elevator and stairways for easy approach and maintenance of the unit. Adequate weather protection will be provided for instruments and operating personnel. Necessary lining and insulation along with fixing materials to limit outside surface temperature to a safe level will be provided. Monorails and hoists required for handling heavy equipment, motors, fans etc. will be supplied along with the steam-generating unit for ease of maintenance. The steam generator and its auxiliaries will be capable of continuous operation at their maximum continuous rating within range of power supply frequency variation from 47.5 Hz to 51.5 Hz. Provision for future installation of FGD system i)

A flue gas desulphurisation (FGD) system may be installed in future to meet the requirements of pollution control and space is provided in the layout.

ii)

Following provisions will be kept for this purpose: a)

Suitability of duct between ID fan and chimney for future installation of FGD system with minimum modification.

M/s. Jhabua Power Ltd.

33

J.M.Environet Pvt. Ltd.

Expansion by addition of 1 x 660 MW Coal Based Super Critical TPP (Phase - 2) At Villages Barela and Gorakhpur, Tehsil Ghansore, District Seoni (Madhya Pradesh)

b)

Final EIA/EMP Report

The ducting and supporting structure to be designed to take care of future Guillotine damper to be installed between the two tap-offs before chimney.

2.4.2

Steam Turbine and Accessories Steam Turbine The steam turbine will be of 3000 rpm, tandem compound, single reheat, regenerative, condensing, three (3) cylinder machine with eight (8) uncontrolled extractions for regenerative feed water heating. The main steam parameters at 100% TMCR load will be 242.23 bar at 565°C before emergency stop valves of HP turbine and reheat steam parameters of 49.34 bar and 593°C at inlet to IP turbine and the condenser pressure will be of 0.1 bar. At turbine valve wide open (VWO) condition the turbo-generator set will be able to operate continuously with a throttle steam flow of about 105% TMCR condition. HP and LP turbine bypass station will be provided as a part of turbine package. The bypass station will act not only as a protection to the unit during pressure rise resulting from sudden load throw off but also enable operation of the unit at loads lower than the controllable range of load. This will also permit quick/hot starts of the unit in case of STG tripping. The bypass station will be sized for a flow corresponding to about 60% of BMCR. A fully automatic gland sealing system will be provided for the turbine, which will have provision for receiving steam from auxiliary steam header during start-up and low load operation. The turbo-generator will be equipped with electro-hydraulic governing system ensuring stable operation under any grid fluctuation and load throw off condition. The turbo-generator will be equipped with an electric motor driven turning gear and manual hand barring gear for emergency purpose. The unit will also be provided with self-contained lubricating oil system for supplying oil to turbine and generator bearings and also to hydrogen seal oil system of the generator. The lubricating oil will be cooled by Closed Circuit Cooling Water System utilising demineralised water as cooling medium. The steam turbine generator will be suitable for tropical climate prevailing in India and indoor installations on reinforced concrete top deck preferably supported on vibration isolation system consisting of steel helical springs and visco dampers.

M/s. Jhabua Power Ltd.

34

J.M.Environet Pvt. Ltd.

Expansion by addition of 1 x 660 MW Coal Based Super Critical TPP (Phase - 2)

Final EIA/EMP Report

At Villages Barela and Gorakhpur, Tehsil Ghansore, District Seoni (Madhya Pradesh)

All auxiliaries like turbine oil purification system, generator seal oil system etc. as well as necessary protective and supervisory system will be provided to ensure trouble-free, safe and efficient operation of the turbo-generator. The unit will be guaranteed to generate 660 MW at generator terminals continuously at cooling water inlet temperature of 33°C. It will also be capable of operating continuously under the HP feed water heaters out of service with total boiler heat duty required under such an operation not exceeding the BMCR heat duty of the boiler and generating 660 MW. Table No. 2.8 DESIGN CRITERIA 1. Turbine throttle steam pressure

242.23 bar

2.

5650C

Turbine throttle main steam temperature

3. Reheat steam temp at turbine inlet

5930C

4. Output under Economic Maximum Continuous 660 MW Rating (EMCR) at Generator Terminals 5. Variations in rated steam temp. & pressure

As per IEC 45 (variations applicable from the offered rated steam inlet parameters)

6. Pressure drop in reheat circuit. i.e. between HP turbine exhaust & IP turbine inlet

10%

7. Back pressure

0.1 bar

8. Turbine Speed

3000 rpm

9. Frequency variation range around rated frequency of Hz

+3% to -5%

of

HPT

exhausts

Pressure

(47.5 Hz to 51.5 Hz)

10. DM water make up to thermal cycle under 1% of throttle steam flow TGMCR conditions (Max.) 11. Final feed water temp. TGMCR condition

290 0C

12. Turbine protection against water induction

As per ASME TDP-1 (Latest Issue)

2.4.3

Cooling Water System and Cooling Tower Closed cycle cooling water system with COC of 5, shall be used to minimize the water requirement for plant. It is proposed to install Induced Final cooling tower. Blow down water from cooling water system shall be used in Ash handling system in order to attain zero discharge.

2.4.4

Coal Handling Plant The entire coal handling plant is designed for catering to 1x600 and 1x660 MW units of which one unit is being installed now and the second unit shall be installed later. Provisions are to be made in the first phase of this coal handling plant for addition of

M/s. Jhabua Power Ltd.

35

J.M.Environet Pvt. Ltd.

Expansion by addition of 1 x 660 MW Coal Based Super Critical TPP (Phase - 2) At Villages Barela and Gorakhpur, Tehsil Ghansore, District Seoni (Madhya Pradesh)

Final EIA/EMP Report

the necessary equipment at a later date to suit this requirement. Coal Handling Plant (CHP) design shall be based on coal GCV of 3150 kCal/kg and maximum daily coal consumption of 22008 Tons (unit-1: 10320T & Unit-2: 11688T). Rated capacity of CHP shall be 1800 T/hr. CHP shall be sized considering input coal size of below 250mm. Two (2) streams, ‘A’ stream and ‘B’ stream are provided. Both the streams of conveyor will be in operation without any standby. Description of CHS for phase 2 Coal from the wagons will be unloaded into wagon tippler hopper by wagon tipplers. Two wagon tipplers are provided in Phase-1 of the project. One additional wagon tippler is envisaged in Phase-2. The wagon tipplers are common to both the units . Apron feeder under the wagon tippler hopper would extract coal from the hopper and distribute it equally onto downstream conveyors which will also be receiving the feed from respective tippler hoppers of phase-1. This in turn will convey the coal to a crusher house, where the incoming coal would be screened and the oversize crushed. Crushed coal would be conveyed to the bunkers, if necessary or stockpiled in the coal stockyard by means of stacker cum reclaimer. Suitable stacking and reclaiming systems is envisaged. The entire conveying system from receipt of coal to conveying up to the bunker will have 100% standby arrangement for reliability. Necessary diversions/ interchanges by means of diverter gates / Belt feeders will be provided at strategic locations of the conveying system so as to ensure adequate flexibility in operation. The storage yard for the power plant is sized considering an average pile height of 10 m. Stockpile capacity is considered as 2,33,760 Tonnes. This storage capacity caters for about Twenty (20) days’ of plant operation for phase - 2 unit with Indian coal having an average calorific value of 3,150 kCal/kg. Coal Receipt, Unloading and Crushing Coal from the mines to plant will be transported by railway wagons (BOX-N type wagons). Considering each wagon carrying 55 tonnes of coal, no. of wagons required per day will be 400 to cater to the daily requirement of 22008 tonnes for the two units. One additional tippler will be envisaged inside the tippler house in Phase-2 to cater to both the units. In phase-2, all the three tipplers will be in operation if wagons of capacity 55T are received at site. The first two tipplers will be operating at 1200TPH each & the third tippler will be operated such that material conveyed by the tunnel conveyor envisaged in phase-2 is equally distributed onto the

M/s. Jhabua Power Ltd.

36

J.M.Environet Pvt. Ltd.

Expansion by addition of 1 x 660 MW Coal Based Super Critical TPP (Phase - 2) At Villages Barela and Gorakhpur, Tehsil Ghansore, District Seoni (Madhya Pradesh)

Final EIA/EMP Report

downstream conveyors by means of flow divider, restricting the conveying rate to 1800 tph per stream. The discharge rate of apron feeder will be suitably controlled by means of a PLC to achieve this preset capacity. In case at a later date if wagons of capacity 71T is received as per revised RDSO guidelines, then only two out of three wagon tipplers will operate meeting the coal requirement per day of both the units.Coal from railway wagons will be unloaded by wagon tippler into Wagon Tippler hopper. Coal from Wagon tippler hopper will be conveyed to crusher house through conveyors. Each tippler hopper will be provided with a belt conveyor of 1800 tph capacity. This will ensure speedy evacuation from the hoppers to facilitate tippling without any constraints. The tracks and hauling system would be sized to handle a full rake of 58 wagons, to ensure quick turnaround of the rakes. The coal received in the tippler hoppers would be conveyed to the crusher house. Incoming coal wagons will be weighed by weighing system provided as an integral part of wagon tippler. Water sprinkler system will be provided for dust suppression during tippling operation. Crushing & Screening System Two numbers of screens & crushers have been considered for phase-1 unit. Additionally two numbers of crushers & screens will be envisaged for phase-2. In crusher house, coal will be screened and crushed to the required size prior to sending to bunkers. Necessary inline magnetic separators and metal detectors will be provided on the conveyors prior to feeding the crusher house. Adequately sized feeder chutes/flap-gates will be provided to have maximum flexibility in the flow of material. Ring granulator type crushers would be employed for crushing (-250 mm to –25mm). Screens will be provided to screen the (-) 25 mm sized coal in the coal. Total four numbers of screens and crushers will cater to the crushing requirement of two units. Screens will be of vibrating grizzley type. The screened and crushed coal will be sent to bunkers directly or stacked in the coal yard. The crushers will be of ring granulator type mounted on vibration isolation system. The crusher house will be provided with freight cum passenger elevator. Stacking / Reclaiming System The stockpile with associated stacker cum reclaimer and yard conveyor would be envisaged for phase-2. The crushed coal will be sent to stockpile when coal is not needed in the boiler bunkers. Stacker cum reclaimer will be provided to stack the coal to a maximum height of 10m. Stock pile capacity is about 233760 Tonnes which

M/s. Jhabua Power Ltd.

37

J.M.Environet Pvt. Ltd.

Expansion by addition of 1 x 660 MW Coal Based Super Critical TPP (Phase - 2)

Final EIA/EMP Report

At Villages Barela and Gorakhpur, Tehsil Ghansore, District Seoni (Madhya Pradesh)

will cater for twenty days for phase -2. Two (2) stockpiles will be formed on either side of stacker cum reclaimer. The stacking capacity will be 1800 tph, and the average reclaiming capacity will be 1600 tph. The peak reclaiming capacity shall not exceed 1980TPH. Necessary drainage facility will be provided. Reclaimed coal will be feeding to bunkers. Bunker Feeding System In the first phase the crushed coal of (-) 25mm size would be fed to either the first phase stockyard or to the steam generator bunkers through series of belt conveyors & travelling trippers. Each row of SG bunkers shall be fed by a single conveyor with traveling tripper. In the second phase, the crushed coal would be fed to either the stockyard of first phase or the second phase or to the steam generator bunkers of second phase through series of belt conveyors & travelling tripper. Other facilities in the plant Dust control in the plant Plain water sprinkler system will be provided for the stock pile. Swinging or swivelling type sprinkler jets will be provided to spray water on the articular section of the stockpile during stacking / reclaiming operation. Dry Fog dust suppression system will be provided at all coal transfer points in the plant. A dedicated compressed air system will be provided for dry fog dust suppression system catering to all the coal transfer points. The bunker bay will be provided with bunker ventilation system Ventilation facilities Fresh air ventilation system shall be provided for all underground tunnels, floor below wagon tippler hopper, etc. Major Equipment Belt Conveyors All conveyors will be of heavy duty design capable of 24 hours continuous duty per day. The conveyors will be designed such that the average apacity will be 80% of rated capacity. The average capacity of the conveyor system will be able to meet the coal requirement of the plant in 14 hours’ operation. Maximum belt speed will be selected based on IS: 11592. Each belt conveyor will be complete unit with the belt, carrying, return, self aligning, impact, transition idlers, pulleys, drive units, belt

M/s. Jhabua Power Ltd.

38

J.M.Environet Pvt. Ltd.

Expansion by addition of 1 x 660 MW Coal Based Super Critical TPP (Phase - 2) At Villages Barela and Gorakhpur, Tehsil Ghansore, District Seoni (Madhya Pradesh)

Final EIA/EMP Report

cleaning devices, deck plate, head frame, tail frame, take-up, hold back, chutes, liners, skirting, and guards. Safety devices such as pull wire switches, belt sway switches, zero speed switches, will be provided. Necessary walkways, maintenance platforms around head, tail pulleys and take-up pulleys, supporting structures and galleries as required will be provided. Metal Detectors: The sensitivity of metal detectors will be sufficient to identify parts of size of minimum 25 mm aluminium spheres at conveyor rated speed across the cross section of conveyed material. The sensitivity will be adjustable. Magnetic Separators: The magnetic separator will be inline belt electro magnetic type with automatic discharge of attracted iron particles. Magnetic separators will be able to attract parts of the size M20 bolts, nuts / 50 kg MS plates / 50 kg MS round bars of L/D ratio within 5. from any position within conveyed material and also allowing for a sufficient clearance between material and discharge belt. Belt Scale: The belt scale will be load cell type and will be continuous operating. Accuracy will be ±0.5%. Provisions for local and remote measurement of instantaneous throughput, totalling, and local signalling of load limits of conveyors. Control of sampler, signals for remote indication and overload alarm will be given in the belt scale. Suitable device for testing the accuracy by test weights will be provided. Coal Sampler Stations: Coal sampling stations will be automatic including multistage sampling and suited to provide one gross sample complying with ASTM D2234. The sampling station will be started manually, locally or from the control room. The sampling station interlocks will be such that the system is started against the direction of material flow. Conveyor Supports, Galleries and Junction Towers: The belt conveyors will be enclosed in suitable closed galleries with provision for adequate central walkway and walkway on either side of conveyors to facilitate inspection and maintenance. All Junction towers will be provided with outside cladding as necessary to have an enclosed structure for dust containment. All junction houses will be provided with adequate hoisting and handling equipment for maintenance purposes.

M/s. Jhabua Power Ltd.

39

J.M.Environet Pvt. Ltd.

Expansion by addition of 1 x 660 MW Coal Based Super Critical TPP (Phase - 2)

Final EIA/EMP Report

At Villages Barela and Gorakhpur, Tehsil Ghansore, District Seoni (Madhya Pradesh)

Belt Cleaners: Suitable belt cleaning devices Pre Cleaner with modular 40 mm thick PU blades and Multi- blade sprung type, blade with tungsten carbide tip with SS base will be provided for cleaning of the external surface of belt. The internal surface of belt will be cleaned by ‘V’ Type cleaner assembly. The blade type cleaners will be spring operated to keep the cleaner blade firmly against the belt. Rubber strips will be adjustable after wear. Crushers: The crushers of 1800 tph rated capacity are provided in Phase-1 of the project. The same crusher will cater to Phase-2 also. Screens: The screens of 1800 tph rated capacity are provided in Phase-1 of the project. The same screens will cater to Phase-2 also. The screens are designed for continuous operation of 24 hrs per day. 2.4.5

Communication System The plant communication system will be provided to facilitate operations by establishing quick communications among the operating personnel stationed at various locations of the plant. The plant Communication System will consist of the following: 

Page and Party System with Master station & Slave Stations.



Telephone systems complete with EPABX, telephone sets in the Power Plant and associated administration buildings.



External telephone system with suitable internet connectivity.



Cellular phone services by cellular operator in Madhya Pradesh state may also be used for the plant communication.

2.5

MITIGATION MEASURES The type of pollution from the power plant is gaseous emissions & Particulate Matter. In addition, wastewater and solid waste will also be generated.

M/s. Jhabua Power Ltd.

40

J.M.Environet Pvt. Ltd.

Expansion by addition of 1 x 660 MW Coal Based Super Critical TPP (Phase - 2)

Final EIA/EMP Report

At Villages Barela and Gorakhpur, Tehsil Ghansore, District Seoni (Madhya Pradesh)

Table No. 2.9 PROPOSED MITIGATION MEASURES S. No. 1.

Environment Air

Mitigation Measure 

ELECTROSTATIC PRECIPITATOR of 99.9% efficiency will be attached to Boiler to maintain the emission concentration less than 50 mg/ Nm3 at Boiler Maximum Continuous Rating (BMCR) Condition.



Second flue of existing stack of 275 m height will be provided for adequate dispersion of Sulphur Dioxide. (NOC for height clearance is attached as Annexure-5)



Provision is made in the plant layout for installing a Flue Gas Desulphuring (FGD) plant in future, if required.



Power plant will use coal burners of proven, advanced design to reduce NOX production, and the boiler furnace will be provided with over-fire air ports to further reduce NOX production.



All the internal roads shall be concreted / asphalted to reduce the fugitive dust due to vehicular movement.



Dust generated in the coal handling area will be minimised

by

providing

suitable

dust

suppression/extraction systems. Boiler bunkers will be provided with ventilation system with bag filters to trap the dust in the bunkers. 

The emissions from the stacks shall be continuously monitored

2.

Water



Waste water will be generated from cooling tower blow down, DM plant, Filter backwash water, Boiler blow down and sanitary wash.



Boiler blowdown: The supercritical boilers do not have a boiler drum. Hence there is no continuous boiler blowdown. However, if the concentration of dissolved solids in the boiler water exceeds a predetermined

M/s. Jhabua Power Ltd.

41

J.M.Environet Pvt. Ltd.

Expansion by addition of 1 x 660 MW Coal Based Super Critical TPP (Phase - 2) At Villages Barela and Gorakhpur, Tehsil Ghansore, District Seoni (Madhya Pradesh)

Final EIA/EMP Report

level due to deteriorating operating conditions, some amount of boiler water can be drained off. The salient characteristics of the blow down water from the point of view of pollution are the pH and temperature of water since suspended solids are negligible. The pH will be in the range of 9.5 to 10.3 and the temperature of the blow down water will be about 100º C since it is flashed in an atmospheric flash tank. It is proposed to lead steam generator blow down after quenching with service water to central monitoring basis (CMB). 

The treated effluents from all streams shall be stored in a guard pond and used for dust suppression and greenbelt development.



Cycle of Concentration (COC) will be maintained at level 5.



The heat cycle makeup requirement shall be met from demineralised water generating acidic and basic effluents. This effluent shall be neutralised and shall be disposed in guard pond or used for ash water.



The sanitary waste water will be treated in packaged STP and used for plantation.



Feasibility of Zero effluent discharge has been examined. The Final effluent will have pH in the range of 6.5 to 8.5 and suspended solids of 100 ppm.

Rain Water harvesting system will be implemented. 3.

Noise



The noise generating sources in the proposed plant will be from Turbine unit, Air compressors, Transformer and Boilers.



All equipments shall be designed for noise levels not exceeding 75 dBA.



Proper PPEs shall be provided to the workers working in high noise area.



M/s. Jhabua Power Ltd.

Proper encasement of noise generating sources will be

42

J.M.Environet Pvt. Ltd.

Expansion by addition of 1 x 660 MW Coal Based Super Critical TPP (Phase - 2)

Final EIA/EMP Report

At Villages Barela and Gorakhpur, Tehsil Ghansore, District Seoni (Madhya Pradesh)

done to control the noise levels below prescribed norms. 

Machines shall be housed in building & provided with acoustic enclosures as required to maintain noise levels within limits.



The operator’s cabins (control rooms) shall be properly (acoustically)

insulated with special doors and

observation windows. 

The

silencers

and

mufflers

of

the

individual

machines shall be regularly checked. 4.

Solid Waste



Ash is the main solid waste generated in the coal based thermal power plant. The quantity of fly ash and bottom ash generated from Phase 2, will be 1.32 MTPA & 0.26 MTPA respectively. The Ash disposal site in Chapter-1 Figure no.



Dry Fly ash will be collected in Silos and sent for use, in Cement

Industry,

Brick

Industry,

Light

Weight

Aggregates, Road Sub-base, Grouting material, Roads / paving - used as filler in asphalt mix for roads, Road enlargement etc. 

Bottom Ash will be disposed to ash pond in semi dry form.



Un-utilised fly ash will be disposed to ash pond adopting high Concentration Slurry Disposal System.

The used oil will be given to authorized recyclers. 5.

Green Belt



Out of the total plant area i.e. 791.79 acres (Phase 1: 406.0 acres & Phase 2: 385.8 acres), about 261 acres (134 acres for phase 1 & 127 acres for Phase 2) of area will be covered under Green Belt / Plantation.



The density of trees will be kept approx. 2500 trees per hectare.



The tree species selected for green belt will include the native species like Neem (Azadirachta indica), Tendu

M/s. Jhabua Power Ltd.

43

J.M.Environet Pvt. Ltd.

Expansion by addition of 1 x 660 MW Coal Based Super Critical TPP (Phase - 2) At Villages Barela and Gorakhpur, Tehsil Ghansore, District Seoni (Madhya Pradesh)

Final EIA/EMP Report

(Diospyros melanoxylon), Teak (Tectona grandis), Khair (Acacia catechu), Karanj (Pongamia pinnata), Gunja (Lannea grandis). Plantation of local species will be done in consultation with DFO as per the CPCB norms.

M/s. Jhabua Power Ltd.

44

J.M.Environet Pvt. Ltd.

Expansion by addition of 1 x 660 MW Coal Based Super Critical TPP (Phase - 2) At Villages Barela and Gorakhpur, Tehsil Ghansore, District Seoni, Madhya Pradesh Final EIA/EMP Report

CHAPTER–III DESCRIPTION OF THE ENVIRONMENT 3.0

INTRODUCTION The main objective behind describing the environment which may be potentially affected are (i) to assess present environmental quality and the environmental impacts and (ii) to identify environmentally significant factors that could preclude project development. The chapter contains information on existing environmental scenario for the following parameters. 1.

Water Environment

2.

Meteorology

3.

Air Environment

4.

Soil Environment

5.

Land Environment

6.

Noise Environment

7.

Biological Environment

8.

Socio-economic Environment

To achieve these objectives, our team monitored the environmental parameters within the core zone and buffer zone (10 km. radial distance) of the project site in accordance with the Guidelines for EIA issued by the Ministry of Environment & Forests, Govt. of India. This chapter and the related discussions contain the results of field studies carried out during the Winter Season 2010-2011. 3.1

STUDY AREA AT A GLANCE 1.

Location: Villages

:

Barela & Gorakhpur

District.

:

Seoni

State

:

Madhya Pradesh

Latitude

:

220 43’ 40”N to 220 44’ 20’’ N

Latitudes

:

790 54’35” E to 790 55’ 35’’ E

M/s. Jhabua Power Ltd.

45

J.M.Environet Pvt. Ltd.

Expansion by addition of 1 x 660 MW Coal Based Super Critical TPP (Phase - 2) At Villages Barela and Gorakhpur, Tehsil Ghansore, District Seoni, Madhya Pradesh Final EIA/EMP Report

2.

Climatology (Winter Season, 2010-11) i)

Maximum Temperature

:

39.7°C

ii)

Minimum Temperature.

:

13.7°C

iii)

Relative Humidity  At 8:30 hrs

:

60% to 78%

 At 17:30 hrs

:

48 % to 63 %

:

723 mm

49032

iv)

Average Annual Rainfall

3. Demography (10 km radius Study Area)

3.2

i.

Total Population

:

ii.

Number of Households

:

9468

iii.

Scheduled Castes

:

6.98%

iv.

Scheduled Tribes

:

60.74%

v.

Literates

:

48.40%

METHODOLOGY ADOPTED For the present study the project site is considered as core zone and the area lying within 10 km radius from the proposed expansion site is considered as buffer zone in which some impacts may be observed on its physical and biological environment.

3.2.1

Data Generation The baseline data for the project site and area within 10 km radius were collected in accordance with the requirement of guidelines and ToR of MoEF. Primary data was collected to set the baseline scenario for the study area. Monitoring was carried out during the Winter Season, 2010-11 for the following parameters:Table no. : 3.1 DATA GENERATED FOR WINTER SEASON, 2010-11

S. No.

Description

1.

Air Ambient air monitoring (24 hourly samples), twice a week continuously. Parameters: SPM, PM2.5, PM10, SO2, NO2, Hg & Ozone (ground Level).

2.

Meteorological parameters on hourly duration at project site. Parameters: Wind Speed, Wind Direction, Relative humidity, Temperature, Cloudiness, Rainfall etc.

M/s. Jhabua Power Ltd.

46

J.M.Environet Pvt. Ltd.

Expansion by addition of 1 x 660 MW Coal Based Super Critical TPP (Phase - 2) At Villages Barela and Gorakhpur, Tehsil Ghansore, District Seoni, Madhya Pradesh Final EIA/EMP Report

3.

Water Water from various locations (surface and ground water samples) in core and buffer zone (10 km radius) once in the season. Tested for physical and chemical parameters according to applicable standards.

4.

Soil Once in a season at various locations in core and buffer zone.

5.

Noise Once in a season at various locations in core and buffer zone.

3.2.2

Secondary Data Collection The baseline data related to the following aspects were collected for the core zone and buffer zone through field survey and secondary sources: 

Details of fauna & flora in the region.



Land use pattern within core zone and buffer zone including the cropping pattern from District Office, Seoni, Madhya Pradesh.



Demography and socio-economic analysis based on last available Census data.



Meteorological data, from India Meteorological Department (IMD), Jabalpur, Madhya Pradesh and from monitoring conducted at site.



Identification of water bodies, roads etc. and collecting data regarding discharge of streams etc. from existing records, within the study area.

In addition to the above samples collected, the data on land use, vegetation, agricultural crops, Forest Area, Wild Life, Revenue Record and meteorological Data were also collected by the field team while meeting with a large number of local inhabitants in the study area and different government departments / agencies. This provided an excellent opportunity to the members of the field team for obtaining an intimate feel of the environment of the study area. 3.2.3

Instrument Used The following instruments were used at the site for environmental baseline data collection work. 1.

Fine Particulate Sampler (APM 550)

2.

Respirable Dust Collector with attachment for gaseous Pollutants, Envirotech APM 460.

3.

Digital D.O. Meter Model – 831 E (CPCB Kit)

4.

Hygrometer

M/s. Jhabua Power Ltd.

47

J.M.Environet Pvt. Ltd.

Expansion by addition of 1 x 660 MW Coal Based Super Critical TPP (Phase - 2) At Villages Barela and Gorakhpur, Tehsil Ghansore, District Seoni, Madhya Pradesh Final EIA/EMP Report

3.3

5.

Sound Level Meter Model SL – 4010

6.

Micro Meteorological Station Model Enviro Wm 251°

7.

Water Level Indicator

8.

Global Positioning System.

Study of Land use/Land Cover around Proposed Project Activity Using Satellite Remote Sensing Data The study was taken up to prepare current land use / land cover within 10 Km radius around the proposed project boundary at Villages Barela and Gorakhpur, Tehsil Ghansore, District Seoni, Madhya Pradesh. (A)

DATA USED Indian Remote Sensing satellite IRS LISS III MX digital FCC (False Color Composite) of current vintage data at 23.5 m spatial resolution has been used for preparation of Land use/ Land cover thematic map of present study area. Survey of India toposheet as a reference map on 1:50,000 scale has been used for preparation of base layer map like road, rail network, contour, drainage, village and rectification of satellite data.

Technical Details  Satellite Image

-

IRS P6 LISS III MX

 Satellite Data Source

-

NRSA, Hyderabad



Software Used

-

Earth

Resources

Data Analysis System (ERDAS) Imagine 9.2 (B) METHODOLOGY The methodology used for the study area consists of following components. (i)

GEOREFERENCING OF SATELLITE IMAGE

Satellite image has been georeferenced by using registered SOI toposheet as a reference map taking suitable Ground Control Points (GCP) points like intersection point of railway, Road network, landmarks and permanent feature. Finally Images were re-projected in UTM projection and their respective zone.

M/s. Jhabua Power Ltd.

48

J.M.Environet Pvt. Ltd.

Expansion by addition of 1 x 660 MW Coal Based Super Critical TPP (Phase - 2) At Villages Barela and Gorakhpur, Tehsil Ghansore, District Seoni, Madhya Pradesh Final EIA/EMP Report

(ii) BASE MAP LAYER CREATION Base map has been prepared using Survey of India Toposheet as a reference map on 1:50000 scale. In base layer linear and point feature like road, rail, canal, village location and plant site have been created in vector data format. Base map layer information has been used for analysis of surrounding feature like road, rail, village location near Plant site activity through superimposed on thematic map for data integration. (iii) INTERPRETATION OF SATELLITE IMAGE Hybrid technique has been used i.e. visual interpretation and digital image processing for identification of different land use and vegetation cover classes based on spectral signature of geographic feature. Spectral signature represents various land use class. Image interpretation keys are developed based on image characteristics like color, tone, size, shape, texture, pattern, shadow, association etc, which enables interpretation of satellite images for ground feature. (iv) GROUND TRUTH DATA COLLECTION Ground data on geo-environmental components of the study area were collected for verification of information of the different features of the study areas, which are responsible for the occurrence of specific spectral reflectance behavioural patterns. The ground truth detailed information on agricultural practices; wastelands, mining, industrial area etc. were collected along with other land features. Ground truth has been carried out for verification of the ground features (esp. one in doubt) interpretation accuracy and reliability of remotely sensed data, which cannot be interpreted directly on satellite imagery. (C)

RESULTS In the present study, both digital image processing and visual interpretation technique were applied to generate output of Land use / Land cover map of study area on 1: 50,000 scale. A standard False Colour Composite (FCC) image has also been generated on the same scale. The study area has been divided into the above major classes of land use for the purpose of computing the area.

M/s. Jhabua Power Ltd.

49

J.M.Environet Pvt. Ltd.

Expansion by addition of 1 x 660 MW Coal Based Super Critical TPP (Phase - 2) At Villages Barela and Gorakhpur, Tehsil Ghansore, District Seoni, Madhya Pradesh Final EIA/EMP Report

M/s. Jhabua Power Ltd.

50

J.M.Environet Pvt. Ltd.

Expansion by addition of 1 x 660 MW Coal Based Super Critical TPP (Phase - 2) At Villages Barela and Gorakhpur, Tehsil Ghansore, District Seoni, Madhya Pradesh Final EIA/EMP Report

M/s. Jhabua Power Ltd.

51

J.M.Environet Pvt. Ltd.

Expansion by addition of 1 x 660 MW Coal Based Super Critical TPP (Phase - 2) At Villages Barela and Gorakhpur, Tehsil Ghansore, District Seoni, Madhya Pradesh Final EIA/EMP Report

M/s. Jhabua Power Ltd.

52

J.M.Environet Pvt. Ltd.

Expansion by addition of 1 x 660 MW Coal Based Super Critical TPP (Phase - 2) At Villages Barela and Gorakhpur, Tehsil Ghansore, District Seoni, Madhya Pradesh Final EIA/EMP Report

M/s. Jhabua Power Ltd.

53

J.M.Environet Pvt. Ltd.

Expansion by addition of 1 x 660 MW Coal Based Super Critical TPP (Phase - 2) At Villages Barela and Gorakhpur, Tehsil Ghansore, District Seoni, Madhya Pradesh Final EIA/EMP Report

3.4

SEISMICITY OF AREA Many parts of the Indian subcontinent have historically high Seismicity. Seven catastrophic earthquakes of magnitude greater than 8 (Richter scale) have occurred in the western, northern and eastern parts of India and adjacent countries in the past 100 years. By contrast, peninsular India is relatively seismic, having suffered only infrequent earthquakes of moderate. The main seismogenic belts are associated with the collision plate boundary between the Indian and Eurasian plates. The hazard map shows contours joining locations of equal expected peak accelerations in rock expressed in percentage. The study area lies in the Seismic Zone II under area of moderate seismic risk by national standards.

M/s. Jhabua Power Ltd.

54

J.M.Environet Pvt. Ltd.

Expansion by addition of 1 x 660 MW Coal Based Super Critical TPP (Phase - 2) At Villages Barela and Gorakhpur, Tehsil Ghansore, District Seoni, Madhya Pradesh Final EIA/EMP Report

FIGURE 3.1: SEISMIC ZONE MAP

M/s. Jhabua Power Ltd.

55

J.M.Environet Pvt. Ltd.

Expansion by addition of 1 x 660 MW Coal Based Super Critical TPP (Phase - 2) At Villages Barela and Gorakhpur, Tehsil Ghansore, District Seoni, Madhya Pradesh Final EIA/EMP Report

3.5

WATER ENVIRONMENT The surface and ground water quality of the study area have been demarcated on the basis of result of water samples collected from different observation points for determining the suitability of water. Key Plan showing the Surface & ground water monitoring location is given as under:

M/s. Jhabua Power Ltd.

56

J.M.Environet Pvt. Ltd.

Expansion by addition of 1 x 660 MW Coal Based Super Critical TPP (Phase - 2) At Villages Barela and Gorakhpur, Tehsil Ghansore, District Seoni, Madhya Pradesh Final EIA/EMP Report

Fig. no 3.2: KEY PLAN SHOWING WATER QUALITY MONITORING LOCATIONS

M/s. Jhabua Power Ltd.

57

J.M.Environet Pvt. Ltd.

Expansion by addition of 1 x 660 MW Coal Based Super Critical TPP (Phase - 2) At Villages Barela and Gorakhpur, Tehsil Ghansore, District Seoni, Madhya Pradesh Final EIA/EMP Report

3.5.1

Surface Water Quality There are two rivers nearby to the project site namely River Temur & River Paryat at a distance of 6.5 & 3.0 kms respectively from the project Site. Rainfall is the only direct source of ground water recharge for the study area in addition to these river bodies. Table No. 3.2 (A) DETAILS OF SURFACE WATER SAMPLING LOCATIONS

S. No.

Location

Direction from the project boundary

Distance (km) from the project boundary

SW1

Temur River

W

6.5

SW2

Paryat River

WSW

3.0

Source: Toposheet & Field Survey Table No. - 3.2 (B) SURFACE WATER QUALITY (Winter Season, 2010-11) S. Test Parameters No

Temur River

1. pH Value 2. Colour (Hazen Unit) 3. Odour

Paryat River

Drinking water Desirable Limit (IS:10500)

Permissible Limit (IS:10500)

8.23

7.79

6.5 - 8.5

No relaxation

5.5 to 9.0