Update on the Toronto Air Rail Link - Transit Toronto

2 downloads 100 Views 1MB Size Report
Dec 5, 2012 - check-in kiosks, flight information display screens and ... to Terminal Three. • Fully enclosed station
Update on the Toronto Air Rail Link Kathy Haley

President, Air Rail Link December 5, 2012

1

Public Board Presentation December 2012 v6

Connecting Canada’s Two Busiest Transportation Hubs Union Station

Toronto Pearson

Downtown Toronto (65 million passengers today and expected to more than double by 2031)

(34 million passengers expected to grow to 50 million passengers by 2031)

2

Toronto Air Rail Link – Program Overview Metrolinx Expertise

Pan / Parapan Am Games

Express Service

The Air Rail Link (ARL), a Big Move priority project, will be delivered and operated leveraging Metrolinx, GO, and PRESTO expertise and capabilities.

We will launch in time for the TO 2015 Pan / Parapan American Games and transform the way visitors experience our city.

The ARL will link the two busiest passenger transportation hubs in Canada – Union Station and Pearson Airport (with stops at Bloor and Weston).

Trains Leave Every 15 Minutes

Dedicated Air Rail Amenities

Economic Development

The amenities available in our stations and on-board our trains will contribute to a productive, enjoyable and stress free trip.

We will contribute to economic growth in the GTHA by providing a direct connection between the financial district of Toronto and the rest of the world.

We will provide fast, reliable trips 25 minutes long departing every 15 minutes.

3

Consultation Video

4

Introducing the Union Pearson Express

Vehicles • • • 5

Tier 4 vehicles manufactured by Nippon Sharryo. Purchase order secured for 18 vehicles to be delivered in 2014 for testing and commissioning. On-board amenities such as luggage racks, washrooms and wifi.

Union Station • • •

6

Design & construction planning underway – construction starts Summer 2013. Located within the Skywalk with direct connections to Union Station and the PATH network. Station amenities include wifi, check-in kiosks, flight information display screens and retail offerings.

Bloor Station • • • 7

Level boarding between platforms and trains. Connections to Dundas-West subway station. All stations are designed to be fully accessible.

Weston Station • • • 8

Attractive station and plaza providing easy access to both ARL and GO services. Convenient passenger pick-up and drop off. All stations will have sheltered waiting areas at the platform level.

Terminal One Station • • • 9

Construction begins Spring 2013. Direct connection to Terminal One and the people mover train to Terminal Three. Fully enclosed station platform behind platform screen doors.

Spur Line • • • 10

Pier & guideway construction underway since June 2012. Three kilometres long and reaching a height of 28 metres above the ground. Construction to be completed Summer 2014.

Timeline and Key Accomplishments Timeline Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2

 Business Strategy and Plan under development

Strategy / Planning

 Over 100 projects identified and underway

2011

Business Planning

Key Accomplishments

2012

2013

2014

 Customer experience program developed

Procurement

Terminal & Spur

Design

 Technology roadmap developed

Const ruction

 Design and construction progress:

Design

Union Station

Procurement

‒ Vehicles – Design complete ‒ Stations - Design 75 % complete ‒ Spur Line - Construction underway

Construction Design

Bloor Station

Procurement Construction

Next Year ‒ Design of all stations complete ‒ Construction will be underway at all locations ‒ Train manufacturing will be underway ‒ Operating plan developed

Design

Weston Station

Procurement Construction Design

Vehicles

2015

Production (A Car)

(C Car)

Delivery

Current 11

Website (www.upexpress.com)

12

www.upexpress.com Thank you