Central Railway Station, Sydney, had developed significant voiding in the foundation ground. Void-filling and re-support of the platform was achieved by ...
Summary Originally built on non-cohesive fill, Platform #2 at Central Railway Station, Sydney, had developed significant voiding in the foundation ground.
In order to minimise the possibilty of damage to the tiled surface of the platform, holes of just 6mm Ø were drilled.
Void-filling and re-support of the platform was achieved by Mainmark using Uretek Deep-Injection with expanding structural resins.
Injection tubes were inserted in these holes and Deep-Injections were made across each part of the area in rotation.
The project was carried out in just 3.5 hours in the middle of the night, thus minimising interference with station activities. Use of very small diameter injection tubes preserved the the tiled surface of the platform.
At each point injection was continued until the platform showed a minimal lift of between 1mm and 3mm.
Objectives The objective was to fill the voids completely and densify the foundation ground to re-support the structure quickly and with minimal inconvenience to station services.
Solution Voids of between 20mm and 70mm were discovered in the foundation ground over an area of approximately 20m2. Uretek Deep-Injection points were established across the area, centering on the void locations.
This established that every section of the platform area had been completely re-supported with the foundation ground bearing the mass of the platform above. The voiding was completely eliminated and re-support of the platform was confirmed. The program was carried out in one night, between 9:30pm and 1am by a two-man technical team, causing minimal disturbance to station activities and almost imperceptible effect on the tiled surface of the platform.
KOA set up prisms along the top of the culvert and used a 'Total Station' to provide real-time feedback on the culvert's movement. The monitoring stopped at the.
The problem for the Hunter's Hill Council engineers was how to best grout behind the sandstone sea wall at Pulpit Point to compensate for the erosion by tidal.
WaterCare Services Ltd was required to fill 300 linear metres of storm-water line beneath Greenhithe,. Auckland. The council-owned pipeline, of DN 150,.
Slab deflection under load was reduced to an acceptable minimum. The whole crossing area was returned to its design levels, stabilised and re- supported.
Slab deflection under load was reduced to an acceptable minimum. The whole crossing area was returned to its design levels, stabilised and re- supported.
Mainmark used a self-levelling cement grout to fill and seal the void in a single day. The placement was continuous, enabling Mainmark to fill the void quickly.
Subsequently natural water ingress, with drains on either side of the track, had eroded away the rail base over time, leaving a large void, around 300mm deep,.
Dec 4, 2013 - cluding philosophy, and with hindsight we can judge that Deacon, a prodigious citer of earlier work, overlooked some clearly relevant antici-.
With Uretek structural resin injection to strengthen the foundation ground, the bridge piers were re-supported and raised back to their exact design levels.
Housed in a collection of former railway buildings near ...... With its buffet car, model and miniature railways as well as gift shops, museum and large car ...... Rail fans can investigate locos and rolling stock and see the James Bond exhibition.